garfunkel
2016-06-07 20:58:48
- #1
Hello,
I need to have a complete screed laid in the bathroom ~3x3.5m (~10m²) and an extension of the existing screed in two other rooms because the knee wall is shifting further outward due to dormer windows.
The screed extension would be ~3x1m (3m²) and ~7x1m (7m²).
In addition, there is the filling of a wall that was torn out 3x0.11m (0.3m²).
As far as I can assess, the rest of the apartment has cement screed.
The build-up consists of some mats (I am not an expert) that appeared to be 2cm thick with 5cm of screed above.
I assume the new screed will therefore also be cement screed?
How long do I need to allow for it to dry?
After what time can I safely walk on the screed and carry out further renovations such as plastering walls, painting, and similar work?
After what time can I start tiling the bathroom without doing any measurements?
After what time can I start laying a floating floor (HDF vinyl with vapor barrier foil) without doing any measurements?
Since screed will only be partially laid outside the bathroom, is it no problem to continue renovating on the other side of the room the day after the screed is laid?
I want to avoid idle times as much as possible but also have enough time for the screed to dry properly.
Can I, except for the bathroom, extend the screed in other ways to avoid long drying times (empty conduits for electrical and heating pipes are laid in the floor)?
In the groove where the wall once was, I originally wanted to lay one or two empty conduits for electricity.
Is this possible at all or is the groove with max. 15cm too narrow?
Do I have cheaper alternatives (except in the bathroom) that I, as a DIYer, could consider for extending the screed?
It should then be just as sensible or more sensible than "classic" screed.
Can you roughly say what it could/should/may cost (20m² screed), so as a rough guideline?
Since I will tile the bathroom myself, where can I borrow a measuring device to be on the safe side and only start tiling when the screed is really dry?
€: There is no underfloor heating anywhere
I need to have a complete screed laid in the bathroom ~3x3.5m (~10m²) and an extension of the existing screed in two other rooms because the knee wall is shifting further outward due to dormer windows.
The screed extension would be ~3x1m (3m²) and ~7x1m (7m²).
In addition, there is the filling of a wall that was torn out 3x0.11m (0.3m²).
As far as I can assess, the rest of the apartment has cement screed.
The build-up consists of some mats (I am not an expert) that appeared to be 2cm thick with 5cm of screed above.
I assume the new screed will therefore also be cement screed?
How long do I need to allow for it to dry?
After what time can I safely walk on the screed and carry out further renovations such as plastering walls, painting, and similar work?
After what time can I start tiling the bathroom without doing any measurements?
After what time can I start laying a floating floor (HDF vinyl with vapor barrier foil) without doing any measurements?
Since screed will only be partially laid outside the bathroom, is it no problem to continue renovating on the other side of the room the day after the screed is laid?
I want to avoid idle times as much as possible but also have enough time for the screed to dry properly.
Can I, except for the bathroom, extend the screed in other ways to avoid long drying times (empty conduits for electrical and heating pipes are laid in the floor)?
In the groove where the wall once was, I originally wanted to lay one or two empty conduits for electricity.
Is this possible at all or is the groove with max. 15cm too narrow?
Do I have cheaper alternatives (except in the bathroom) that I, as a DIYer, could consider for extending the screed?
It should then be just as sensible or more sensible than "classic" screed.
Can you roughly say what it could/should/may cost (20m² screed), so as a rough guideline?
Since I will tile the bathroom myself, where can I borrow a measuring device to be on the safe side and only start tiling when the screed is really dry?
€: There is no underfloor heating anywhere