So, I want to report again. It’s been so long that I first had to reread my own posts. Due to the new baby and a complicated birth as well as the drastic changes a baby brings (Metime has expired) nothing really happened here for a good 5 months (almost) :D
It’s been moving forward again for two months.
But for the update:
Middle purlin: finished, supported – with old oak beams from a historical building supplier
Horizontal barrier: finished – for 4,000 EUR …that was really a bargain (built up and bitumen membrane inserted)
Ceiling in between: started, new support beams and wooden floor decking are in (except for the area where the interior insulation of the gable wall needs to be raised)
Interior insulation: started, will probably be finished the week after next
Drywall partitions: when the wood prices rose so much, we decided, due to the not-so-large price difference anymore, to have the interior walls done with sand-lime bricks by the masons.
Outside service:
As announced, the middle purlin was supported through an outsourced contract by the craftsman company where my husband did his apprenticeship. They also immediately replaced the rotten sole plate and fixed two leaks in the roof area. We were very satisfied with the price/performance ratio… but you do have some advantages when you’re still on good terms with the people.
For the interior insulation, after much back and forth, we switched to another mason (my husband also knows him from the past but didn’t work there) and are now actually having a two-layer build with aerated concrete blocks and insulation wool. Except for the original architect, everyone else (different architect, two masons) preferred a two-layer build instead of Multipor. At first, I had doubts about moisture (condensation from inside) and the support beams. But I wasn’t enthusiastic about Multipor due to the lack of load-bearing capacity. We had to swallow a bitter pill; I hope we made the right decision. For this reason, additional ring beams will also be installed, which will lend some support to the static structure.
We are actually having the crooked outer wall torn down. We didn’t want the wall to get further out of alignment in the end after we finish everything down below. Extra cost around 10,000 EUR. Yay :D First, the new inner shell will be built, then the outer wall (outer shell) will be removed piece by piece and rebuilt.
Own work:
We installed the support beams for the office, partially installed the new wooden ceiling, dismantled old electrical wiring and laid Deltathene where the second shell (outer wall) will go (against moisture). Everything went fairly unspectacularly. When supporting the office floor and installing the new support beams, it was a bit fiddly but otherwise went without incident.
Schedule:
Goal by the end of February: interior insulation and interior walls finished, electrical work at least started, preferably also finished, but I expect that only in March.
Goal by the end of April: electrical work finished, windows installed, further development of the office hopefully mostly completed.
Oh yes: And since we can’t go on vacation, we got a hot pot now... maybe not so smart to throw 5k out without being finished. But I was pouty.
Photos are partly not current but older.
