Thank you very much for the congratulations. :)
I had already written the text in January but never sent it because we shortly after had problems with the cistern/former slurry pit. More on that in a separate post.
Update
So, things are slowly moving forward with us now. After our craftsmen stood us up again last Monday for the floor slab, apparently due to a defect with the excavator, they resumed their work today. Thank God, our schedule is no longer as generous as planned due to the upcoming baby. At least for the noisy trades.
External service:
The first section covered around 35 m² and cost us just under 2,400 EUR for the work performed and disposal of the excavated material, excluding materials (concrete, steel, etc.). The excavation alone (concrete, earth, bricks, cups, socks, and whatever else people liked to throw in earlier) would have cost us almost 1,000 EUR for disposal in a container ourselves. Therefore, we are satisfied with the price for the shitty work.
The second section, which is currently being worked on, is more difficult: since there used to be a small calf stable here with a drainage channel and everything that goes with it, the concrete layer is much thicker than in the area of the first section that was already in residential use. That means the craftsmen have quite a bit to do – and due to the currently low ceiling heights (about 2.30 meters, with the ceiling beams even only about 2.20 meters), only a small excavator fits in the room. In the previous area, there was significantly more room with ceiling heights of 3.00 to max. 6.00 meters. This will also drive up the costs. The target clear height in this area is about 2.40 meters or just below. This only affects our living room.
I hope the craftsmen will push through quickly – there are still well over 100 m² to be done in 5 sections.
Own work:
In the meantime, we were able to move the staircase on the already new floor slab. It had to be moved to the other side of the wall, i.e., from the later kitchen area to the heating room because the space for the kitchen with kitchen island and possibly a stove would have been too small. We spent about 4 full working days on covering the old wall, installing two new drywall walls, making the ceiling cutout, relocating the staircase, and covering the staircase along with the door. The door including covering at the staircase will be removed again later, but it was necessary because we already have living spaces upstairs. Drywall, paint, etc., are not yet done; that will make sense at a later time. We also need to be patient with ordering the new staircase.
What was particularly annoying was that the floor heating, cut open at the top, just wouldn’t stop leaking. Unfortunately, the supply line didn’t close completely. Our plumber’s emergency service said to completely shut off the floor heating, and they would come tomorrow. Fortunately, we still found a new actuator and were able to solve the problem ourselves even at 9 p.m. Now, the plumber just has to reconnect the floor heating pipes. Luckily, this is possible without much effort in our case. That means we avoid having to break up the entire laminate including dry screed in the area of the floor heating circuit.
Schedule:
Goal by the end of February: floor slab finished, find craftsmen for the horizontal barrier in the masonry (unfortunately, no one is keen on that either), and complete the drywall walls for the storage rooms and the entrance area – as far as that is possible by then.
Goal by the end of March/beginning of April: raising of the intermediate ceiling (ceiling between the office upstairs and kitchen downstairs) finished, horizontal barrier finished, masonry work for the new front door and windows on the ground floor (lintels remain, window openings deepen) finished and windows and front door for the ground floor ordered.
Since we have never really been able to stick to the schedule so far, I do not expect that we will manage all trades this time either ;)
Obstacles:
My husband will have 6 wisdom teeth plus (somehow there are still very small wisdom teeth hidden in the jaw oO) removed at the beginning of February. This means a forced break for the area of own work.