Bieber0815
2016-02-15 07:26:37
- #1
Would you accept the first paragraph as it stands, or do you find it permissible?
- When is the contract conclusion planned? How many months are there from contract conclusion until the end of September 2017? (More than 12? --> I would find that outrageous.)
- What type of contract is it (GU/GÜ or BT)? If BT, the soil condition should be the risk; the corresponding clause can be attempted to be deleted.
- Of course, a regulation beyond the end of September is missing (example: 50 euros per working day for completion after the end of September)
- I would write a concrete date; "end" is so flexible ...
- I would delete _one_ date and the 2-month clause (the date then fairly at the end of September).
Whether I would accept all this depends on my alternatives.