Payment plan okay - 13% after the floor slab?

  • Erstellt am 2017-07-02 01:18:58

Arifas

2017-07-10 14:24:40
  • #1
I have thought about it and the risk is actually too high. If the company went bankrupt, we might suffer the consequences for a very long time and, due to the family situation, we can't quickly recover from it. I will address it that way.

Is there possibly the option to transfer the money to a secure account until, for example, the completion of the shell construction? Then the general contractor would have the security that we can pay, and we would have the assurance that the money won't disappear in case of insolvency?

And how can I find out how the general contractor is financially positioned?
 

markus2703

2017-07-10 14:49:32
  • #2
You can make all payments, for example, via a [Notaranderkonto]. However, the [GU] must agree, and it will certainly cost quite a bit.

You then pay into the account, and the notary releases the funds according to your instructions. But even there, the payment schedule would have to be changed to postpone the due date. The [GU] usually sets up the schedule in a way that allows them to work with your money already.

So the only option is to negotiate and possibly change providers.

I have the impression that larger construction companies tend to have more "customer-friendly" payment plans in the contract.
 

RobsonMKK

2017-07-10 14:50:55
  • #3
A point of reference is the Bundesanzeiger. Otherwise, if you are in the BHB, you can also obtain a Creditreform report (e.g.).
 

Arifas

2017-07-10 15:02:08
  • #4
I have found the Bundesanzeiger and also the GU. Unfortunately, I don't understand a word of it [emoji20]. Would it be possible for someone to take a look, and I would send the link via PM?
 

AndreasPlü

2017-07-11 13:15:02
  • #5
50% for the shell construction is okay, it should not or hardly be more. % at the time of signing is not acceptable, for which service then? The first 5% for completion of the building application documents maybe, but better only due after the building permit has been granted. Here lies a cost trap: What actually happens if the application is not approved as is and needs to be revised after the 5%? Or if the design is crap?
 

Maxi2012

2017-07-11 14:31:04
  • #6
We have paid the first 6% after completion of the foundation slab... and we are building with a basement, which means all earthworks were carried out beforehand...
 

Similar topics
14.11.2011Shell construction still this year15
05.09.2015Cracks in masonry (shell construction)14
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
24.04.2015Buy tiles during shell construction24
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
27.02.2015Purchase shell construction and complete it including financing15
11.02.2016Cost per cubic meter of built-up shell space14
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
07.05.2016Buying a shell construction - Experiences21
08.08.2016Payment before or after completion of the construction phase?51
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
28.02.2017Are securities customary for completion and warranty?24
20.04.2017Payment plan with 35% after the shell construction, okay?10
05.05.2017Rough construction flat-rate offer - forgotten necessary items11
06.09.2017Add a wind catch later to the shell construction17
19.08.2018Strategically well-planned handover completion under building supervision11
29.09.2020Building permit before completion of development31
14.11.2021Sell an apartment from a two-family house immediately after completion34
01.07.2022Construction delay without completion. The house simply is not finished21

Oben