Kitchen stockpile, price fixing - price increase after expiration?

  • Erstellt am 2025-06-27 10:49:55

nordanney

2025-06-27 12:31:47
  • #1

Why should the planner be proactive? YOU want to buy something and haven’t gotten off your backside for 2 years. There are reasons for that. But the kitchen builder doesn’t have to care about that.

You don’t quarrel if you don’t sign a contract. If the kitchen builder pressured me a lot, he would already be suspicious to me anyway, especially if I don’t need the kitchen until later. And then a kitchen for almost 40k!!! Crazy to order it so early and even crazier to pay such a large amount that early...
I only buy my things when I can roughly estimate the timeline. At least roughly.

The trust was justified. He did not go bankrupt. He can still deliver the kitchen to you.
AND: This is merely a price increase of 8%. Roughly corresponds to the pure general inflation of the last 24 months. I find it more than fair that he does not want to increase his profit even more.

Bad for you personally. But bad that you (unfortunately) caused yourself with prior notice.
 

hanghaus2023

2025-06-27 14:52:14
  • #2


Hello Merle123



But the kitchen fitter is not to blame for that.



3.5% is in my opinion a fairly common rate for 1 year. The down payment was certainly contractually regulated. So you had no problem at the time of signing the contract. The postponement of the date has nothing to do with it. The increased costs arise only after the original contract has expired.



Your idea is, in my opinion, neither covered by the contract nor usual.



He can only do so now. Then the additional costs really only arose after the final order.



That means the price guarantee has expired. The parties can negotiate a new price.

3.5% of 40k is 1400 euros. Why 3000?



The claim for 3.5% is, in my opinion, justified, but not more. Negotiate again. Only commission the follow-up when you agree.



I can understand you. But you have also handled your money quite carelessly.

Whether you can get out of the contract so easily is questionable. What does the contract say about cancellation conditions? Otherwise, the Construction Contract Act applies. The contractor is at least entitled to reimbursement of services already rendered and lost profit.
 

wiltshire

2025-06-27 16:44:09
  • #3
Hello Merle123,
Your kitchen dealer is behaving absolutely correctly and within the agreed terms. And the agreement is not "wrong" either. That it took so long for you is not his fault. That you possibly bought too early and made a deposit is also not his fault. Of course, the kitchen dealer does not invest the deposit anywhere to generate interest, and a deposit is not a loan business – so why should there be interest? On the other hand, the dealer took a risk with the fixed price and would have had to finance interim price increases from his margin. Why should he still do that now?

You are not alone with such an experience – we were even in such a situation that we bought the kitchen before we had the building permit. The often-cited "one" doesn’t do that.

House connection box—just call it "bad luck" and look forward to a great kitchen in the new house. Admitting your own mistakes doesn’t kill you. To what extent you allow a €3000 price increase to ruin your quality of life is up to you alone. As long as you try to shift the blame to your kitchen dealer with thoughts of extracontractual set-off, you won’t find peace. It’s not worth it.
 

Gerddieter

2025-06-27 17:13:11
  • #4
I would pay it and write it off as a learning experience and save myself the trouble.

If you hadn’t signed in 2022 but only today, the price increase would have been more than 3.5%...

What somehow remains unclear to me: if 3.5% price increase = 3000 euros - did you then order a kitchen for round about 100k?
GD
 

kbt09

2025-06-27 17:34:14
  • #5
The 3000 euros probably refer to interest loss and price increase



I have to disagree here, you certainly had a few meetings, could look around the showroom, possibly try out appliances, etc. That also costs money. Of course not 40% of the order value, but you also bought a 2-year price guarantee. And especially since 2022, kitchen and appliance prices have risen quite a bit. With the now 1,600 euro additional price, you are more than well off.
 

wiltshire

2025-06-27 17:59:16
  • #6
I had the same thought and roughly calculated in my head 85,000€. That’s about the entry level at Boffi. Then I saw the 15,000€ as a 40% down payment. According to that, the purchase price would be 37,500€. A price increase of 3.5% would then correspond to 1,312.50€. Anyone who gets 3,000€ out of 15,000€ through interest in 3 years has an average performance of just under 7%. That is satisfactory, but cannot be achieved with an investment classified as "low risk". The numbers are not entirely consistent, but that does not matter, it’s only theory anyway outside the contractually agreed terms.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
05.11.2016Deposit to seller - pay or withhold?28
28.05.2017Plundering the Riester contract - for less need for credit?16
27.02.2018Old home savings contract - what should you do with it?31
19.11.2018Fixed price commitment - price increase after expiration?25
06.02.2021The developer requires a down payment to start drawing42
19.09.2021Price increase - Our construction company wants 21.4% more211
30.03.2022Terminate the contract with the general contractor "early"22
25.08.2022Price increase despite fixed price!56
22.05.2022Construction company price increase of 25% – Expired fixed price guarantee58
24.06.2022Additional costs after the expiration of the price commitment14
18.10.2022GU demands a price increase on the entire house122

Oben