Issuance of the building permit?

  • Erstellt am 2017-05-01 17:38:39

11ant

2017-05-04 13:10:55
  • #1


Salto Postale was also along those lines. But I fear some offices even model themselves on MA 2412 :-)

The duration of reviewing a building application also correlates somewhat with what actually needs to be checked: some development plans specify the number of floors, floor area ratio/floor space index and possibly the roof pitch; for others every front yard shrub is mentioned with all seven first names, how many square meters a bay window is allowed to have, and the color shade of the garbage enclosure. That naturally takes time.

At least in small municipalities the best way to speed things up is probably to submit the application in person (not at the info counter, but to the processor, who might have time for follow-up questions right away). They then immediately see how likeable the applicant is, and the stamp gets applied more easily :-)
 

sirhc

2017-05-04 13:21:39
  • #2
The first time 3 months, the second time one week. :D

The city we currently still live in is said to take 8 months until the building permit.
 

Nordlys

2017-05-04 13:42:36
  • #3
I want to be honest. I can understand the frustration of many citizens about the slow work of authorities. There are a variety of reasons for this. In the rarest cases, it is due to a lack of willingness to work by the people involved. Point 1) Building authority and flood of applications. Construction is going on like there is no tomorrow. The banks throw money at you. Every gap is being filled. Large numbers of demolitions as well. Applications are piling up. Point 2) is homegrown: The enormously rigid staffing table in the public service. Roughly now you have to start setting up the staffing plan for 2018. Positions that are not included there practically do not exist. If you want to hire people beyond the staffing plan, this is theoretically possible but practically impossible because decisions by the city council or district council or others are required to change it during the current year... By the time that is done, the year is over. Point 3): Substitutions. Let’s assume that office xy is well staffed according to the staffing plan and the positions are filled. But: Out of 10 employees, 5 are sick, four of them longer-term due to complicated issues. Now find a substitute, limited to the duration of the illness of... Theoretically possible, practically quite impossible. There are usually no substitute positions held open in the staffing plans either. So: de facto no backups. Point 4) Particularly annoying for the citizen. It is a hierarchical system. If cases are not watertight clear, none of the subordinate clerks want to take responsibility, but rather refer it to the superior. The bottleneck. Especially when the superior is a character-weak control freak who only trusts himself, pulls everything to himself, makes himself indispensable, and then goes on vacation and rehabilitation.---- Point 6) Centralization of processes. Best example, has nothing to do with construction, but you can see it well here: Federal Employment Agency. Only job centers left. Only large units. Telephone hotlines, call centers... The building permits should go back to the local level. (The processing of Hartz 4 etc. as well, by the way). A building must be approved at the town hall. District and regional government only in disputed cases. That would certainly be faster. In big cities, building affairs should belong to the level of district offices. Just a little excursion....Karsten
 

markus2703

2017-05-11 15:04:07
  • #4
Not even 24 hours... Construction within a development plan, small municipality. World still in order.
 

HERR_bau

2017-05-11 15:25:04
  • #5
In our Hessen region, people say about 3-6 months are normal. But it depends on too many things to really say that as a general rule. Basically, you have to ask the people from the street/place/community/city where you are building, and even that probably wouldn’t be representative enough...
 

Egon12

2017-05-12 07:51:58
  • #6
planned according to the development plan, exemption granted after 4 weeks, 6 weeks later the deep construction worker arrived.
 

Similar topics
31.10.2008Is a building permit also required for a carport and equipment shed?13
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
19.03.2015Questions about the building permit21
28.11.2024Neighbor's lawsuit against approved building permit46
18.03.2016Influence of the neighbor in building permit18
16.01.2017No building permit as long as the land is not developed?10
31.12.2017Winter garden conversion - building permit required or permit-free?15
08.01.2018According to the law, the building permit is automatically granted if12
22.01.2018Building on still foreign land - Waiting for building permit25
21.06.2018What must be included in the building permit? Legal certainty?19
29.08.2018Filling up a raised plot of land to make it level - building permit required?16
18.09.2018Immission protection concerns self-service gas station - building permit?20
24.10.2018Broker sells house without current building permit. Notary costs?25
26.01.2019Building permit from 1931 not adhered to35
08.04.2019Can the garage be moved after obtaining the building permit?11
09.09.2022Experiences with forest conversion in the context of building permits in Brandenburg20
28.08.2019Building permit for terrace roofing14
06.09.2019Construction project and building permit feasible?97
04.11.2019Is only part of the building permit enforceable? How long is the building permit valid?42

Oben