Issuance of the building permit?

  • Erstellt am 2017-05-01 17:38:39

Deliverer

2017-05-02 10:52:53
  • #1
A little over eight months.
 

Nordlys

2017-05-02 12:02:52
  • #2
4 weeks. Proposal for acceleration. Submit the application by hand at the city.
 

Tanita

2017-05-03 06:58:40
  • #3
Our preliminary building inquiry is currently running as follows:
- talked to the building authority by phone and in person, as there were still some minor uncertainties
- personally submitted and DISCUSSED the preliminary building inquiry
- 2 weeks later: request for plans in a different scale and powers of attorney (no, this was never mentioned before!)
- personally submitted again
- 2 weeks later a call: the data is now in the system and is being processed.
=> this is supposed to take about 4-6 weeks now...
... we will see...
 

PhiTh

2017-05-03 09:24:39
  • #4
What saved us a lot of time was that we personally and directly approached the neighbors regarding an exemption and asked for their consent or had them sign the corresponding form. For us, this took one week. Through the municipality, such a process usually takes 6 weeks or even longer.
 

dohuli

2017-05-03 09:31:59
  • #5
Sent by us during the summer holidays. 17 calendar days later (including changes, i.e., additional correspondence in between) we had the building permit. No preliminary building inquiry was sent, but beforehand we asked the building authority at an appointment whether the project was feasible as planned.
 

Nordlys

2017-05-03 10:39:28
  • #6
Building in an existing development area without a development plan: Longer processing time, as §34 applies.
Building in an area with a development plan or a new development area with a development plan: If the development plan is adhered to, it is usually completed within 4 weeks.
Here in SH: first the city/the municipality/the office to which the municipality belongs examines it. If you know the person in charge there, you hand it over, they flip through it, ask if necessary, stamp it, then it goes to the district, where it is practically approved immediately. Karsten
 

Similar topics
28.12.2013Conversion of agricultural land to building plot, objection, building authority, building regulations12
30.01.2014Preliminary building inquiry before purchasing property okay, can this information be trusted?15
28.06.2015Knee wall height / Proposal from the building authority33
17.06.2016Further procedure in case of rejection of the preliminary building inquiry35
20.06.2016Building Authority Approval10
16.07.2016Purchase Agreement for Land - Building Window - Preliminary Building Inquiry12
22.02.2017Building inquiry - What is relevant?12
11.04.2017Building authority wants site inspection116
04.07.2017Problems with the building authority due to soil slips and retaining walls!27
13.07.2017Do you need the building approval from the building authority?15
22.09.2017Telephone construction inquiry rejected13
07.11.2017What questions should be asked to the building authority?19
14.08.2019Building inquiry / Letter to the District Office12
02.09.2019Problems with neighbor's encroachment and building authority11
30.11.2020Building Authority Problems - Purchased a Defective Plot56
26.11.2021Preliminary building inquiry, sale of partial plots, procedure21
13.03.2023Preliminary construction inquiry for land purchase: What should be considered?24
20.03.2024Submit a building inquiry in Hamburg16
15.04.2024Is the involvement of the nature conservation authority necessary for a preliminary building inquiry?14
30.06.2024Should the building inquiry with exemption be rejected?11

Oben