my husband and I are currently caught up in house-building fever – planning and approval completed.
Now we have received the offer from our construction company – but we don’t really know whether the offer is reasonable or not.
A brief info:
enclosed volume 905 m³
usable living area 139 m²
double garage and basement
heating system: heat pump
As a woman, I am not very familiar with this – please excuse me if I express myself incorrectly anywhere.
Now to the cost estimate – I would be very grateful if you could give me a few statements about where we stand, whether it is reasonable or not.
I only have net prices here, so everything plus VAT!
Excavation 7000,-
Shell construction 85365,-
Scaffolding 2366,-
Carpenter 23040,-
Tinsmith 4011,-
Window manufacturer 16000,-
Garage 2700,-
Stove builder (pellet Swedish stove) 2700,-
Plasterer 20000,-
Screed 3200,-
Heating, ventilation, sanitation 31000,-
Shutters 2500,-
Tiler 7300,-
Floor layer 5738,- with laminate
Doors 4000,-
Work planning and construction management 11000,-
The total including VAT is about €270,000 – unreasonable?!
Maybe you can give us a brief assessment or tell us where the extreme outliers are. We don’t want to get ripped off.
Also – is €11,000 for work planning reasonable?
Would be very grateful for your help!!
Best regards
Simone
my husband and I are currently caught up in house-building fever – planning and approval completed.
Now we have received the offer from our construction company – but we don’t really know whether the offer is reasonable or not.
A brief info:
enclosed volume 905 m³
usable living area 139 m²
double garage and basement
heating system: heat pump
As a woman, I am not very familiar with this – please excuse me if I express myself incorrectly anywhere.
Now to the cost estimate – I would be very grateful if you could give me a few statements about where we stand, whether it is reasonable or not.
I only have net prices here, so everything plus VAT!
Excavation 7000,-
Shell construction 85365,-
Scaffolding 2366,-
Carpenter 23040,-
Tinsmith 4011,-
Window manufacturer 16000,-
Garage 2700,-
Stove builder (pellet Swedish stove) 2700,-
Plasterer 20000,-
Screed 3200,-
Heating, ventilation, sanitation 31000,-
Shutters 2500,-
Tiler 7300,-
Floor layer 5738,- with laminate
Doors 4000,-
Work planning and construction management 11000,-
The total including VAT is about €270,000 – unreasonable?!
Maybe you can give us a brief assessment or tell us where the extreme outliers are. We don’t want to get ripped off.
Also – is €11,000 for work planning reasonable?
Would be very grateful for your help!!