Is it sensible to prepare the plot before starting earthworks?

  • Erstellt am 2022-02-11 10:12:52

Hendrik1980

2022-02-11 10:12:52
  • #1
Dear forum,

is it sensible to take care of the development of the property before starting the earthworks? Specifically, it concerns a plot of about 1500 sqm. Earthworks are to begin in July and shell construction in September.

We would like to use the time until summer to have electricity, water, and sewage connected to our property. Is this productive or should this only be started in conjunction with the earthworks?

Are there certain sequences to be observed in the coordination?

Looking forward to feedback!
 

driver55

2022-02-11 17:43:25
  • #2
Usually done together with the earthworks, otherwise the excavator has to come twice...

Coordination? You just have to get electricity/water/sewage/Magenta to the site promptly and almost simultaneously.

In any case, do not start before the building permit/approval.
 

Pitiglianio

2022-02-11 19:28:10
  • #3
This is about the question of whether the OP should/can have the utility lines brought to/on the property.

If the position of the house and the future connection room are fixed,
what should speak against having this done before the building permit and earthworks. The utility providers are responsible for this and receive the corresponding development fees from the builder.
 

Yaso2.0

2022-02-11 23:29:17
  • #4
We initially thought the same and then let it be.

Now the suppliers have laid the connections and the upper part of the pipes still sticks out a bit from the ground, so you can basically see a kind of cover. Sorry, no idea what it’s called…

During the earthworks, the excavator driver would constantly have to somehow avoid those things, and in my opinion that would be very complicated.
 

Similar topics
05.04.2015Property reserved. Financing is pending52
28.09.2016Evaluation of earthworks offer14
16.01.2017No building permit as long as the land is not developed?10
24.04.2017Buying land without a soil survey?13
13.06.2017Plot fully developed, additional costs?10
22.01.2018Building on still foreign land - Waiting for building permit25
15.05.2018Water, gas, and electricity - disconnection and reconnection?10
08.04.2019Earthworks costs in Bavaria15
15.05.2019Are the house connections already one meter on the property?16
30.09.2019Floor plan optimization of a single-family house with a basement on a small plot178
11.11.2019House connections for pipe handle property10
04.05.2020Assessment of land - hillside location15
19.10.2020Building permit with an excavation permit27
08.09.2020Earthworks costs, hillside house14
05.04.2021Attach to property access planning65
15.01.2021Development costs for a plot in the second row35
28.11.2020Expensive plot + single-family house 155 sqm + cellar KFW40+, financeable?60
05.06.2021New building connection costs, especially wastewater17
15.03.2022Cost planning for earthworks33
29.10.2022Is the property fully developed? - Cable is partially missing10

Oben