Inspection before completion (no stairs and exterior work)

  • Erstellt am 2021-10-23 21:27:57

Jelena1994

2021-10-23 21:27:57
  • #1
Hi everyone,

I have been following along for months and now I am opening a topic myself because I simply don’t know what to do anymore.

I sold my apartment on 01.11.2021 and am currently having a single-family house built through a developer in BW. The move-in date was verbally agreed to be 01.11.2021, but the contract states 7 months after the start of construction (which was in February). We actually got along well at first, but month by month everything became more suspicious.
Anyway, the stairs (I had to look for the stair manufacturer myself because the developer only informed us after signing the contract that he does not have a wooden stair partner) will only be installed at the end of November.
What is still missing today:
- no stairs, only a construction stair
- on the outside there is no facade, only insulation (according to the contract this can only be done after the promised 7 months of construction time)
- you can still see all the work from the fiber optic or geothermal drilling as the deep holes have not yet been filled back in with soil/humus
- sliding door will only come at the end of December
- electrical additional price list on the cost calculation that I receive from the developer by PDF is not correct, as it has not been updated since July
- no light well (according to the contract this can only be done after the promised 7 months of construction time)
- no rainwater downpipes (I assume as long as the exterior facade is not on, there will be no rainwater downpipes either)
- garage and all exterior work are missing (according to the contract this can only be done after the promised 7 months of construction time)

Inside it is still chaotic but by the end of the week electricity, heating and the bathroom are supposed to work (floor + painting work are also finished).
My question:
I have to move in on 01.11 because I have no other option except a hotel. But since there is only a construction stair until the real stairs come and as described above several works have not yet been completed, I read online that it is a high risk to accept handover. However, the following sentence gives me hope:
'' No implied acceptance exists if the client explicitly refuses acceptance before the handover despite moving in and using the building and informs the construction company that despite the move-in there is no formal acceptance.''
So can I move in but refuse acceptance?

I am afraid that if I move in, the developer will slow down even more and simply stop making an effort….. So I am in a dilemma because I actually have to move in….
Since I had to choose the stairs myself, the developer shifts the blame onto me and thus does not pay a penalty of €40 per day for the delay, even though 7 months have actually already passed, but verbally 01.11 was agreed….

Many thanks in advance for the answers!
 

ypg

2021-10-23 22:23:34
  • #2
We seem to be missing information? The argument is not understandable as it stands. Whoever moves in implicitly accepts. But to get to the principle: Of course, it is really unfortunate that the house is not finished yet. However, this situation is common. You are not the only one and not in an extraordinary situation where the apartment or previous house must be terminated or vacated, and the future house is not yet ready or habitable. There are plenty of options: for example, a holiday apartment and parallel storage of the furniture. Every second builder I know does it that way. So do I.
 

Nida35a

2021-10-23 22:33:18
  • #3
Holiday apartment as a temporary solution,
ask if you could stay longer in the old apartment,
offer compensation for this.
Don’t drive yourselves crazy
 

Jelena1994

2021-10-23 23:02:05
  • #4
Before signing the contract, it was verbally agreed that I wanted a wooden staircase, but the developer had offered a steel staircase in the purchase contract. The developer then said it was no problem to arrange a wooden staircase. However, after signing the purchase contract, it turned out to be a problem, because a few months later I was told to take care of the staircase myself. According to the developer, I am to blame for the fact that they cannot be finished, since I did not want his staircase. The problem was, however, that the screed was installed much too late due to the long window deliveries, so the staircase builder was only able to take measurements two months ago, and that is not my fault. Who is right here?

Moving into a holiday home is not an option because I have 3 pets. My wife and child have already moved to her mother’s, which is totally okay for me. But with my cat and two dogs, that is not an option.
So what speaks against moving in and at the same time refusing to accept the handover and record this in the protocol? Or is this not legally possible due to the missing staircase (fire protection....)? The moving company is already booked for the upcoming Saturday.
 

ypg

2021-10-23 23:10:22
  • #5

Verbal is nothing.

Well then… it is up to you to explore your options.

See above. I wrote that in #2!
 

Smialbuddler

2021-10-24 08:01:38
  • #6
Apart from the disadvantageous legal aspects - I doubt that moving to a construction site is really better for your animals. With dogs, depending on their character, it might work, but I have heard from cat owners about really big problems when moving into a quiet, finished (but unfamiliar to the cat) house. So the move itself will also be stressful. I would recommend that you carefully reconsider whether a holiday apartment or something similar is really that much worse. At least it is quiet and clean there - and reliably lockable. There are also animal-friendly providers. Another option: a cat boarding facility!
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
27.07.2013Average construction time for a semi-detached house with a basement11
01.03.2015The developer does not build according to the plan14
13.06.2015New construction with developer / construction drawing documents23
15.03.2016Developer changes plot size25
10.09.2016Construction financing and contract with the developer24
25.08.2019Solid prefab house or developer - experiences?33
21.07.2017Buying a terraced house from a developer - contract content?71
30.12.2017Take over the insurance from the developer after handover of keys?15
29.05.2018Buying a house from a developer - required documents33
30.08.2019Must developers indicate immense embankment height/costs?12
04.03.2019Client-side while building with a property developer16
14.11.2019Scheduling apartment handover and moving20
06.01.2020House purchase, prefabricated house from the developer with land10
13.07.2020Developer does not want to offset lump-sum damages with installments19
04.08.2020Surprising price increase just before signing17
13.10.2022National move - long distance - how to find a moving company?108
22.12.2024Floor plan changes for end-terrace house from the developer133
25.12.2023Behavior in case of imminent delay by the property developer48

Oben