Jelena1994
2021-10-23 21:27:57
- #1
Hi everyone,
I have been following along for months and now I am opening a topic myself because I simply don’t know what to do anymore.
I sold my apartment on 01.11.2021 and am currently having a single-family house built through a developer in BW. The move-in date was verbally agreed to be 01.11.2021, but the contract states 7 months after the start of construction (which was in February). We actually got along well at first, but month by month everything became more suspicious.
Anyway, the stairs (I had to look for the stair manufacturer myself because the developer only informed us after signing the contract that he does not have a wooden stair partner) will only be installed at the end of November.
What is still missing today:
- no stairs, only a construction stair
- on the outside there is no facade, only insulation (according to the contract this can only be done after the promised 7 months of construction time)
- you can still see all the work from the fiber optic or geothermal drilling as the deep holes have not yet been filled back in with soil/humus
- sliding door will only come at the end of December
- electrical additional price list on the cost calculation that I receive from the developer by PDF is not correct, as it has not been updated since July
- no light well (according to the contract this can only be done after the promised 7 months of construction time)
- no rainwater downpipes (I assume as long as the exterior facade is not on, there will be no rainwater downpipes either)
- garage and all exterior work are missing (according to the contract this can only be done after the promised 7 months of construction time)
Inside it is still chaotic but by the end of the week electricity, heating and the bathroom are supposed to work (floor + painting work are also finished).
My question:
I have to move in on 01.11 because I have no other option except a hotel. But since there is only a construction stair until the real stairs come and as described above several works have not yet been completed, I read online that it is a high risk to accept handover. However, the following sentence gives me hope:
'' No implied acceptance exists if the client explicitly refuses acceptance before the handover despite moving in and using the building and informs the construction company that despite the move-in there is no formal acceptance.''
So can I move in but refuse acceptance?
I am afraid that if I move in, the developer will slow down even more and simply stop making an effort….. So I am in a dilemma because I actually have to move in….
Since I had to choose the stairs myself, the developer shifts the blame onto me and thus does not pay a penalty of €40 per day for the delay, even though 7 months have actually already passed, but verbally 01.11 was agreed….
Many thanks in advance for the answers!
I have been following along for months and now I am opening a topic myself because I simply don’t know what to do anymore.
I sold my apartment on 01.11.2021 and am currently having a single-family house built through a developer in BW. The move-in date was verbally agreed to be 01.11.2021, but the contract states 7 months after the start of construction (which was in February). We actually got along well at first, but month by month everything became more suspicious.
Anyway, the stairs (I had to look for the stair manufacturer myself because the developer only informed us after signing the contract that he does not have a wooden stair partner) will only be installed at the end of November.
What is still missing today:
- no stairs, only a construction stair
- on the outside there is no facade, only insulation (according to the contract this can only be done after the promised 7 months of construction time)
- you can still see all the work from the fiber optic or geothermal drilling as the deep holes have not yet been filled back in with soil/humus
- sliding door will only come at the end of December
- electrical additional price list on the cost calculation that I receive from the developer by PDF is not correct, as it has not been updated since July
- no light well (according to the contract this can only be done after the promised 7 months of construction time)
- no rainwater downpipes (I assume as long as the exterior facade is not on, there will be no rainwater downpipes either)
- garage and all exterior work are missing (according to the contract this can only be done after the promised 7 months of construction time)
Inside it is still chaotic but by the end of the week electricity, heating and the bathroom are supposed to work (floor + painting work are also finished).
My question:
I have to move in on 01.11 because I have no other option except a hotel. But since there is only a construction stair until the real stairs come and as described above several works have not yet been completed, I read online that it is a high risk to accept handover. However, the following sentence gives me hope:
'' No implied acceptance exists if the client explicitly refuses acceptance before the handover despite moving in and using the building and informs the construction company that despite the move-in there is no formal acceptance.''
So can I move in but refuse acceptance?
I am afraid that if I move in, the developer will slow down even more and simply stop making an effort….. So I am in a dilemma because I actually have to move in….
Since I had to choose the stairs myself, the developer shifts the blame onto me and thus does not pay a penalty of €40 per day for the delay, even though 7 months have actually already passed, but verbally 01.11 was agreed….
Many thanks in advance for the answers!