Max1978
2022-07-14 15:27:02
- #1
Hello everyone, I hope you can help me a little. We had our prefabricated house delivered the day before yesterday, so far everything went well. Our problem is that the plot is not yet developed, the work for the development will begin in the next two weeks. The site manager now wants the house to be connected, the energy provider says that this is not the usual procedure. There is nothing in the house yet that could be connected and even then they could use the construction power, which is available. However, I am a layman and a bit overwhelmed. As a layman, I would have said to use the construction power as long as the house is not developed. For the construction power, a provisional overhead line was installed that supplies two plots, so if we want to be connected before that, it can be done, but it does not change the fact that it is only construction power, and the street would have to be dug up twice. I hope I was able to explain my question well :-) Best regards, Max