House construction planned, what sums must one reckon with today?

  • Erstellt am 2023-01-01 16:22:45

i_b_n_a_n

2023-01-01 18:14:06
  • #1
oh, the development plan is generous. Almost everything is allowed ;-)
 

Yosan

2023-01-01 18:55:23
  • #2
Oh Rabenau... I'm surprised there are still plots available there at that price. I would have expected more. How far along is the [Baugebiet] already? It doesn't look like it's under construction yet to me?!
 

rulor1992

2023-01-01 18:57:19
  • #3


The construction area is not yet developed.
I don't know when it is supposed to be developed.
Rabenau is not exactly the top choice when it comes to building plots, I would say.
The next town is 20 km away.
 

Yosan

2023-01-01 19:20:55
  • #4
I know where Rabenau is ;) It will still take quite some time before the houses can be built there. Keep that in mind when planning your budget. And always keep an eye on interest rates so you can strike at the right moment as soon as the building area is developed enough.
 

WilderSueden

2023-01-01 21:17:00
  • #5
The critical point in any cost estimation is likely to be the exact definition of "upscale standard." You can quickly end up with much higher costs than targeted; 3000 €/sqm is more the minimum here, even in Saxony, 3500 €/sqm is probable, 4000 are possible ;)
 

Yosan

2023-01-01 21:41:09
  • #6
It is apparently to be built in Central Hesse, not in Saxony.
 

Similar topics
18.06.2015The plot must be developed. The general contractor says this is a priority!35
16.01.2017No building permit as long as the land is not developed?10
13.06.2017Plot fully developed, additional costs?10
16.05.2022Which plots are the best in this building area (with plan)?17
29.10.2022Is the property fully developed? - Cable is partially missing10