bau.herr
2017-07-20 18:37:44
- #1
Hello everyone
Foundations and the base slab were poured at our site. There was a large pump truck and several trucks with concrete arrived. From the delivery note I could see that the concrete was sometimes discharged at our site well over 90 minutes after loading at the plant. Water was sometimes added, which was also not listed on the delivery note.
Now the question: is it a problem that sometimes "old" concrete was used and water was added unplanned?
In a regulation I read, it said that ready-mixed concrete in the mixing truck should be discharged within 90 minutes.
I am worried whether this is okay.
Thanks in advance
Best regards
Foundations and the base slab were poured at our site. There was a large pump truck and several trucks with concrete arrived. From the delivery note I could see that the concrete was sometimes discharged at our site well over 90 minutes after loading at the plant. Water was sometimes added, which was also not listed on the delivery note.
Now the question: is it a problem that sometimes "old" concrete was used and water was added unplanned?
In a regulation I read, it said that ready-mixed concrete in the mixing truck should be discharged within 90 minutes.
I am worried whether this is okay.
Thanks in advance
Best regards