So, after quite a bit of back and forth, we are now close to signing.
Do I still have major blind spots or are certain cost calculations absolutely off? We will lay out the garden ourselves at our leisure, and I have left the kitchen out of the calculation.
Turnkey house price including base slab and photovoltaic system including sample credit (15 months fixed price guarantee) |
415,000 € |
Plot (approx. 450 m²) |
96,000 € |
Earthworks/Excavation |
36,000 € |
Utility connections |
12,000 € |
Permits and surveying |
6,000 € |
Construction electricity and water |
3,500 € |
Road closure (if necessary) |
2,500 € |
"Carport" with wood shed (primarily a wood shed with canopy) |
14,000 € |
Insurance + building expert (prefab house expert twice) |
6,000 € |
Unforeseen costs |
19,525 € |
Transport, assembly, crane, mobile crane included
Work and safety scaffolding included
Waste container included
Construction site toilet included
Specialist site management included
Soil report included
Architect, building application, submission plans for house
Static calculations, construction plans, etc. included
Heat calculation and energy certificate included
Proofs and certificates for grants and subsidies included
Construction plan and execution drawings included
Technical documents, applications for water, electricity, telephone, sewage included