Developer does not want to offset lump-sum damages with installments

  • Erstellt am 2020-07-11 16:48:05

Ötzi Ötztaler

2020-07-11 19:10:04
  • #1
Is the flat-rate compensation also due if the construction contract is terminated by you? Off to the lawyer with you, don’t rely on lay opinions from the internet.
 

Gerd1908

2020-07-11 19:24:26
  • #2
Well, it’s a developer contract and not a construction contract. At the moment, the land belongs to the developer. The options are: - just pay everything and hope for some kind of compensation - rescind the entire contract (which we obviously don’t want after 2.5 years of construction). In the latter case, one would also have to dispute whether one would receive any damages (for example, interest on committed capital). We’re going to the lawyer soon, I thought there were other victims who have experience with unscrupulous developers (who rebrand every few years). Thanks to you all!
 

danixf

2020-07-11 19:37:00
  • #3

With such delays, a visit to the lawyer is long overdue. As of now, it still looks lucky, but it could have turned out differently and who knows how much money would have been lost.
 

nordanney

2020-07-11 19:48:49
  • #4
If you don’t pay, however, the apartment won’t be finished, handed over/accepted, and you will not become owners due to the lack of ownership transfer. Complicated situation, for which I would definitely involve a lawyer (why haven’t you consulted one yet after 1.5 years of delay??).
 

Pinky0301

2020-07-11 20:23:35
  • #5
Our property developer also wanted us to pay the full price back then and refund us the penalty later. Fortunately, our purchase contract stated that it would be offset against the installment. Does it say anything like that in your contract? I can understand your bad feeling, I would also be worried about my money.
 

Gerd1908

2020-07-11 21:24:20
  • #6

Unfortunately, nothing like that is in the contract. However, we received a letter from them with the invoice for the 2nd installment asking us not to reduce the invoice and to settle these matters (compensation for delay) mutually with installment 6. We are about to pay installment 5 (if the construction has reached this status), but we have already received an invoice for special requests "tiles" that will be implemented later. That would now be like an advance payment. They add that special requests cannot be offset against the "future compensation claims due to construction delays," as this is excluded from the proceedings (no idea what proceedings they are referring to). The purchase price installments have been assigned to their financier 100%. Furthermore, it states: "Disputes over compensation and guarantees (...) can only be conducted by the developer company after completion of the construction project."
So they are now excluding what they requested back at installment 2 (to settle matters with installment 6) again. Hence this absolutely bad feeling. We will be seeing a lawyer next week, who is already advising us on this matter. My intention was to maybe find like-minded people here. If I am a one-off case here, I am happy for everyone else! Until now, I only knew of such construction delays with projects like the Berlin airport.
 

Similar topics
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
12.03.2013What is the maximum rate for a net salary of 3,000 euros?24
18.02.2014Massive problems with the builder - is contract termination possible?33
04.07.2015House contract with financing condition, lawyer wanted10
22.07.2015Young family wants to buy a house, but does the installment fit?15
11.08.2015What can I realistically afford as a rate?51
03.01.2016surprising bill, no cost estimate12
03.05.2016Please evaluate the payment plan25
21.07.2017Buying a terraced house from a developer - contract content?71
30.12.2017Take over the insurance from the developer after handover of keys?15
26.06.2020The developer has let us down - what to do now?42
10.09.2019Trouble with the property developer, don't know what to do anymore13
16.10.2019Rent for construction dryer in final invoice/builder - legal?14
09.02.2020Developer | Special Request | Cost Assumption38
17.07.2020Real estate transfer tax - developer and construction company same person11
06.01.2021Purchase from the developer at the end of the year - Financial assessment12
17.07.2022Single-family house: Is the rate realistic? How much house can we afford?177
08.12.2022New rate twice as high - experiences107
25.12.2023Behavior in case of imminent delay by the property developer48
01.01.2024How much installment can we afford?42

Oben