Cost planning for earthworks

  • Erstellt am 2022-03-03 13:22:46

Hafenstraße

2022-03-14 13:26:58
  • #1


Unfortunately, all this sounds very negative and much more pessimistic than how one always imagined "building a little house." But in the end, you are absolutely right! Nobody will have to live in the house except us, and that is how we are treated.

But it wasn’t meant to be that naïve either. First, the soil surveyor has to go to the site, then the civil engineer (who in my case is more of a "vertical builder"...) and then the house manufacturer may carry out the planning for the foundation slab. That still has to be coordinated with the utility companies, who have their own civil engineers to bring us (waste) water and electricity to the house. That will definitely be fun!
 

netuser

2022-03-14 13:36:37
  • #2


Although the whole thing should not be taken naively or lightly, don’t drive yourself crazy now and don’t see everything in a negative light. You are already thinking about it and taking care of it. In the end, hopefully, you will be able to say that it was easier than expected.

At least for me personally, that was the case, and beforehand, I was also annoyed or worried about many unclear details, especially with surveyors and civil engineers. During and after the execution, it was all "not so bad" and went well or easier than expected.

You also have a reliable partner with Weberhaus, so good conditions have already been created here for them to think along a bit and not leave you completely out in the cold ;)

So, understand the requirements and get your own offers. Then it will work out.
 

Hafenstraße

2022-03-14 13:39:06
  • #3


Great, so we already agree on something :D That’s how I imagined it too (see above).



Exactly, nothing can be done there. But at least you can point out to the customer that such a thing exists. Personally, I didn’t know that because I’ve never dealt with construction before. What’s wrong with the architect advising me to ask about it during the cost calculation? Actually nothing, but he chose simply to name 500 euros, which we then undoubtedly relied on. The same applies to the surveyor. I have already asked surveyors for quotes myself (for which I actually pay my site manager very well), which were indeed somewhat cheaper. But still about 2000 euros above the planned amount. Most of it depends on the standard land value and house size in combination with HOAI and fee schedules, so 0% negotiable. Accordingly, all parties involved could have known here that 3000 euros for the surveying of a single-family home in a relatively expensive large city in NRW will never be enough. By the way, according to the city’s statement, I do need an official site plan, whose price is also fixed (independent of the surveyor). Nevertheless, I’m very grateful for tips. But writing about this here is probably not allowed, right?



I hope you’re right! As I said, if an earthworks contractor gives me an offer within the budget (or now slightly above), I’ll take it immediately. I just want to be sure I won’t end up paying 20 or 30,000 euros more in the end.

The drainage will take place near the surface. For the water from the roof, we have a separate sewer connection that leads to a soakaway outside the new development area. So, additional connection costs are coming up, especially because of the location in the water protection area. For this reason, the sewer must be specially encased.
 

WilderSueden

2022-03-14 13:47:09
  • #4
Have the empty conduits for the utility providers installed right away during the civil engineering work. Then you'll have much less trouble with the utility providers. Usually, not everyone digs up the trench again; the first one creates an empty conduit system, and the others use it. In cases like this, only careful planning in advance and not relying on estimates helps. That didn’t happen, and the situation is already dire. Still, I would recommend you go through the calculation again as quickly as possible and critically question all items. Simply so that you know how much additional cost will actually come your way and can plan accordingly in case of doubt.
 

netuser

2022-03-14 13:50:30
  • #5


Basically, you are right that people are often not sufficiently advised/informed. Many variables are indeed difficult to capture in advance, but in the examples given, one could actually point out the circumstances and possible sources of information...

Regarding the "official site plan," I still advise you to check more thoroughly whether this is actually required. I almost don't assume so. According to my information, it is only required (?) if there are contaminated sites and no building plot has yet been formed. Otherwise, it is cheaper without it.
 

netuser

2022-03-14 13:54:31
  • #6


No, as far as I understand, the MSH is included and provided by Weberhaus. It is installed by them during the construction of the foundations or the slab. You probably won't have much trouble with the utility companies themselves, except for scheduling after the house is delivered, etc.
 

Similar topics
21.10.2011Floor slab insulation "Yes!" or "No!"14
02.12.2013Are surveying costs negotiable with the surveyor?10
02.09.2013Survey plan: What is its content and where can I get it from10
02.08.2014Is the financing for a single-family house too tight?15
15.08.2016Civil engineer contradicts structural engineer27
14.03.2017Brainstorming ideas for a house on a steep slope13
28.02.2019Construction costs: Single-family house in Baden-Württemberg 2019 (KFW 40 plus)35
04.06.2020Civil engineer proposes deviations from the drainage plan10
09.09.2020Calculation of a prefabricated house19
16.04.2024KfW40+ with a basement inside or outside the thermal envelope?38
14.09.2021Civil engineer calculates excavator performance by tons - experiences?21
03.04.2024Floor Plan Feedback Single-Family House - Weberhaus23
28.09.2024Architect commissions surveyor without the homeowner's consent.45

Oben