Pfadfinder87
2019-04-14 08:05:15
- #1
Hello,
I wanted to ask for your assessment of the cost breakdown from our architect. Preliminary information about the construction project:
Construction will be within an existing building
Construction site setup
Construction site setup including crane 4,800.00 €
Scaffolding work 3,500.00 €
Demolition work
Bricks approx. 210m² x 10€ 2,100.00 €
Battens, purlins, rafters approx. 210m² x 12€ 2,520.00 €
Gutters + downpipes approx. 23m x 15€ 345.00 €
Gable masonry approx. 35m² x 60€ 2,100.00 €
Dismantling windows, roller shutter boxes, front door, entrance stairs 3,700.00 €
Demolition of interior walls approx. 40m² x 20€ 800.00 €
Demolition of exterior masonry approx. 20m² x 40€ 800.00 €
Blocking up/cutting of chiseled components 30m x 15€ 450.00 €
Creating new stairwell opening in the ground floor ceiling 1,000.00 €
Demolishing floor coverings + screed on ground floor approx. 140m² x 20€ 2,800.00 €
Construction
Reinforcement steel 5,000.00 €
Ground floor: support pads, lintels, steel beams approx. 15m x 250€ 3,750.00 €
Masonry exterior walls new attic approx. 105m² x 90€ 9,450.00 €
Separation layer for masonry approx. 100m² x 8.50€ 850.00 €
Existing chimney raise 1,500.00 €
Ring beam approx. 65m x 60€ 3,900.00 €
Lintels approx. 13m x 85€ 1,105.00 €
Load-bearing interior walls attic approx. 29m² x 90€ 2,610.00 €
Non-load-bearing interior walls ground floor + attic approx. 80m² x 65€ 5,200.00 €
Roof
Roof truss approx. 11m³ KVH x 550€ 6,050.00 €
Carpentry approx. 390m x 8€ 3,120.00 €
Small metal parts 800.00 €
Eaves + verge boarding approx. 40m² x 36€ 1,440.00 €
Roof slope OSB boards approx. 150m² 3,600.00 €
Collar beam ceiling approx. 68m² x 95€ 6,400.00 €
Insulation roof slopes + collar beam ceiling approx. 220m² x 23€ 5,060.00 €
Roof battens approx. 210m² x 9€ 1,890.00 €
Verge + eaves boards approx. 58m x 6€ 348.00 €
Underlay membrane approx. 210m² x 10€ 2,100.00 €
Clay roof tiles approx. 210m² x 16€ 3,360.00 €
Ridge tiles approx. 13.8m x 39€ 538.00 €
Verge tiles approx. 30m x 30€ 900.00 €
Special tiles – penetrations 300.00 €
Vent pipe caps with flexible hose 400.00 €
Chimney flashing + cladding 1,200.00 €
4 roof windows with external shutters 6,800.00 €
Solar collectors approx. 4m² 3,800.00 €
Zinc gutters approx. 28m x 30€ 840.00 €
Rainwater downpipes approx. 8m x 35€ 280.00 €
Drain supports + bends 76.00 €
End drains + leaf guards 100.00 €
Front door canopy 1,760.00 €
Interior work
Front door system 6,200.00 €
Windows/doors with roller shutters and exterior window sills 28,000.00 €
Heating: condensing boiler 11,870.00 €
Underfloor heating ground floor + upper floor 8,600.00 €
Plumbing installation 7,600.00 €
Electrical 10,000.00 €
Decentralized ventilation system 8,770.00 €
Insulation of basement ceiling approx. 135m² x 18€ 2,430.00 €
Screed ground floor + attic 234m² x 20€ 4,680.00 €
Bathrooms 11,500.00 €
New stairs to attic 6,000.00 €
Interior doors 8 x 450€ 3,600.00 €
Floor coverings approx. 234m² x 60€ 14,040.00 €
Interior window sills 450.00 €
Interior plaster and painting work 12,000.00 €
Exterior plaster + insulation approx. 300m² x 87€ 26,100.00 €
Total costs: 271,282.00 €
What was completely neglected is the outdoor area, since the garden is already landscaped and fences are set up and will remain. What we still need to add:
Garage door: 6,000.00 €
Terrace: 5,000.00 €
Basement insulation outside and bitumen coating: 2,000.00 €
Paving driveway: 10,000.00 €
+ the "soft costs" of
Building permit fees 1,200.00 €
Architect for building application 5,950.00 €
Structural engineering and thermal insulation 3,000.00 €
and for internal calculation about 20,000.00 € for kitchen, lamps, and other furnishings
That brings us to a total of 324,432.00 €
A few questions are on my mind:
- How is it with the Energy Saving Ordinance, is exterior wall insulation mandatory as well as a ventilation system when renovating?
- Is a timber frame construction cost-neutral compared to masonry? What are possibly other advantages and disadvantages? (Our main previous argument for timber frame construction is the speed as well as the easier change of room layout if necessary)
Thanks!
I wanted to ask for your assessment of the cost breakdown from our architect. Preliminary information about the construction project:
Construction will be within an existing building
[*]Year of construction 1971
[*]Exterior dimensions approx. 13m x 11.50m
[*]Gable roof 33°
[*]A 1.20m knee wall will be built
[*]Change of room layout within the existing building
[*]Complete renovation
Construction site setup
Construction site setup including crane 4,800.00 €
Scaffolding work 3,500.00 €
Demolition work
Bricks approx. 210m² x 10€ 2,100.00 €
Battens, purlins, rafters approx. 210m² x 12€ 2,520.00 €
Gutters + downpipes approx. 23m x 15€ 345.00 €
Gable masonry approx. 35m² x 60€ 2,100.00 €
Dismantling windows, roller shutter boxes, front door, entrance stairs 3,700.00 €
Demolition of interior walls approx. 40m² x 20€ 800.00 €
Demolition of exterior masonry approx. 20m² x 40€ 800.00 €
Blocking up/cutting of chiseled components 30m x 15€ 450.00 €
Creating new stairwell opening in the ground floor ceiling 1,000.00 €
Demolishing floor coverings + screed on ground floor approx. 140m² x 20€ 2,800.00 €
Construction
Reinforcement steel 5,000.00 €
Ground floor: support pads, lintels, steel beams approx. 15m x 250€ 3,750.00 €
Masonry exterior walls new attic approx. 105m² x 90€ 9,450.00 €
Separation layer for masonry approx. 100m² x 8.50€ 850.00 €
Existing chimney raise 1,500.00 €
Ring beam approx. 65m x 60€ 3,900.00 €
Lintels approx. 13m x 85€ 1,105.00 €
Load-bearing interior walls attic approx. 29m² x 90€ 2,610.00 €
Non-load-bearing interior walls ground floor + attic approx. 80m² x 65€ 5,200.00 €
Roof
Roof truss approx. 11m³ KVH x 550€ 6,050.00 €
Carpentry approx. 390m x 8€ 3,120.00 €
Small metal parts 800.00 €
Eaves + verge boarding approx. 40m² x 36€ 1,440.00 €
Roof slope OSB boards approx. 150m² 3,600.00 €
Collar beam ceiling approx. 68m² x 95€ 6,400.00 €
Insulation roof slopes + collar beam ceiling approx. 220m² x 23€ 5,060.00 €
Roof battens approx. 210m² x 9€ 1,890.00 €
Verge + eaves boards approx. 58m x 6€ 348.00 €
Underlay membrane approx. 210m² x 10€ 2,100.00 €
Clay roof tiles approx. 210m² x 16€ 3,360.00 €
Ridge tiles approx. 13.8m x 39€ 538.00 €
Verge tiles approx. 30m x 30€ 900.00 €
Special tiles – penetrations 300.00 €
Vent pipe caps with flexible hose 400.00 €
Chimney flashing + cladding 1,200.00 €
4 roof windows with external shutters 6,800.00 €
Solar collectors approx. 4m² 3,800.00 €
Zinc gutters approx. 28m x 30€ 840.00 €
Rainwater downpipes approx. 8m x 35€ 280.00 €
Drain supports + bends 76.00 €
End drains + leaf guards 100.00 €
Front door canopy 1,760.00 €
Interior work
Front door system 6,200.00 €
Windows/doors with roller shutters and exterior window sills 28,000.00 €
Heating: condensing boiler 11,870.00 €
Underfloor heating ground floor + upper floor 8,600.00 €
Plumbing installation 7,600.00 €
Electrical 10,000.00 €
Decentralized ventilation system 8,770.00 €
Insulation of basement ceiling approx. 135m² x 18€ 2,430.00 €
Screed ground floor + attic 234m² x 20€ 4,680.00 €
Bathrooms 11,500.00 €
New stairs to attic 6,000.00 €
Interior doors 8 x 450€ 3,600.00 €
Floor coverings approx. 234m² x 60€ 14,040.00 €
Interior window sills 450.00 €
Interior plaster and painting work 12,000.00 €
Exterior plaster + insulation approx. 300m² x 87€ 26,100.00 €
Total costs: 271,282.00 €
What was completely neglected is the outdoor area, since the garden is already landscaped and fences are set up and will remain. What we still need to add:
Garage door: 6,000.00 €
Terrace: 5,000.00 €
Basement insulation outside and bitumen coating: 2,000.00 €
Paving driveway: 10,000.00 €
+ the "soft costs" of
Building permit fees 1,200.00 €
Architect for building application 5,950.00 €
Structural engineering and thermal insulation 3,000.00 €
and for internal calculation about 20,000.00 € for kitchen, lamps, and other furnishings
That brings us to a total of 324,432.00 €
A few questions are on my mind:
- How is it with the Energy Saving Ordinance, is exterior wall insulation mandatory as well as a ventilation system when renovating?
- Is a timber frame construction cost-neutral compared to masonry? What are possibly other advantages and disadvantages? (Our main previous argument for timber frame construction is the speed as well as the easier change of room layout if necessary)
Thanks!