Construction time

  • Erstellt am 2014-04-20 12:26:23

jomeier75

2014-04-20 12:26:23
  • #1
Our developer estimates 9 months for a semi-detached house (solid construction) from delivery of the base plate to moving in. Is that realistic? Please provide your assessment.
 

toxicmolotof

2014-04-20 13:34:35
  • #2
I am just wondering how a delivered floor slab is transported...

But aside from that, it probably depends on the logistical performance. It can work well, but it doesn't have to.

How are we supposed to assess that? The best hint can be given to you by former clients of the [GU].
 

Bauexperte

2014-04-20 13:39:19
  • #3
Hello,


You probably mean "pouring" the foundation slab?

As for the rest, I would say - if the semi-detached house does not consist of numerous recesses and/or a round design - your general contractor is a clever one :D

Easter greetings from the Rhineland
 

jomeier75

2014-04-20 14:20:38
  • #4
Sure, I meant the pouring of the foundation slab. That was in April, and move-in was scheduled for December. Now it’s April again and we are still in interior construction (screed dried, walls prepared for painting). We had sold our apartment with a 3-month buffer until the end of March and are now living in temporary accommodation. I just wonder if this could have been foreseen. We only recently found out that our developer had not agreed on penalty clauses with the craftsmen, and we ourselves did not include any such agreement in our purchase contract. Otherwise, someone else probably would have been awarded the contract.
 

Bauexperte

2014-04-20 15:42:48
  • #5
Hello,

there probably wasn’t much information for you in advance, right?


It doesn’t matter "at all" to you "what" your general contractor agreed or didn’t agree with his subcontractors; you "should have" had a fixed handover date/guaranteed construction period stipulated before signing the contract!

To answer your question: such an approach is usually not so unusual if no construction period is guaranteed in the contract. Why should your general contractor hurry, when he has all the time in the world?

"Had" and "if" won’t help you anymore now ...

Easter greetings from the Rhineland
 

jomeier75

2014-04-20 19:03:26
  • #6
Would have certainly liked to have a contractual fixation of the completion. Only if demand is greater than supply, we did not see ourselves in a position to enforce it and now have to bear the consequences.
 

Similar topics
06.05.2012Cost for semi-detached house11
03.08.2012Contract Supplement to the Construction Contract by the Developer36
18.10.2012Ancillary construction costs and general expenses for a new semi-detached house14
27.07.2013Average construction time for a semi-detached house with a basement11
21.11.2013Is the floor slab still possible this year?15
15.11.2013Build a semi-detached house with different developers?10
23.06.2014Developer charges heavily for replanning - justified?12
21.12.2016Semi-detached house - choice between split water heat pump and gas/solar12
25.08.2019Solid prefab house or developer - experiences?33
23.01.2017What to do if the construction time is not met15
06.03.2017Single-family house or semi-detached house?37
04.03.2019Client-side while building with a property developer16
23.07.2019Semi-detached house feasible for 400k?18
12.11.2019Semi-detached house yes or no65
17.07.2020Real estate transfer tax - developer and construction company same person11
26.04.2021Does a developer have to dispose of earth excavation?16
04.05.2021Recommendation for terrace partition for a semi-detached house wanted16
06.06.2023Estimation of construction time for the new build of a semi-detached house17
29.04.2024Construction cost estimation of a semi-detached house experiences13
23.06.2025Is the foundation slab and house protected against moisture with bubble foil? Experiences?33

Oben