Construction company - start of construction, communication. Tips, experiences?

  • Erstellt am 2021-01-23 11:42:17

hausnrplus25

2021-01-23 17:06:26
  • #1


I think that’s a good tip.

Unfortunately, we also haven’t set a construction start date, only a completion date with corresponding "penalties". We considered specifying a time frame for a long time.
But in the end, the construction start depends on the building permit, and it is understandable that the company can only schedule you once the building permit is granted. Furthermore, a completion time must be specified, otherwise a digger might just show up and then nothing happens for months again.
We decided against it, due to the uncertain point of the building permit, also because we want to contract out the civil engineering and concrete work ourselves and also somewhat out of trust in the company. Let’s hope it wasn’t a mistake.

Setting the building permit as a deadline is a good tip for everyone who hasn’t signed a contract yet.

Wishing you much success for an early start!
 

ypg

2021-01-23 17:22:17
  • #2
We also haven’t set anything. When we inquired after the building permit, we were told that they wait so many weeks... I assume that the general contractors only start planning on their wall plan board once the building permit is available. Before that, there is no magnet with our name on it. Then the back-and-forth shuffling on the yearly planner begins. It will be the same for you.

Of course, as a general contractor you don’t mention that you are one of many and will be last in line. You basically have to queue up at the back.

Are you working in the office? One less construction manager. He is on site almost every day... the office staff handling the email account have no authority...

Little. The boss was irritable.

No, we were not persistent. If they tell us that no one will work on the site every day and that this is just how it is, then that must be right. At the neighboring plots, sometimes no one showed up for a week...

And then Corona. Instead of 4 craftsmen only 2, which delays things, then some in quarantine... even more delays. This drags out multiple construction sites, and the last ones suffer the most.

What else comes to mind: more expensive houses are prioritized because the general contractors earn more with those. Maybe that’s why you are being fobbed off more than others.
 

Robbs84

2021-01-23 21:49:35
  • #3
Hello everyone,

thank you very much for the many tips and experiences!



Yes, we also expected about 12 months from building permit to move-in, for us the processing time of 8 weeks after building permit for the execution planning was included, after that we thought it would start...



We do not want a lawyer or to terminate the contract at this point due to the incalculable cost and time risks. However, having the contract checked by a lawyer again is a point we keep in mind if things continue this way...



We have an expert who also says that a start in winter is possible, if you want there are means and ways. We are building here in the Hamburg region, there has been hardly any snow so far and temperatures fluctuate between -3 at night and +6 during the day. However, there are certainly 3-4 days with 3-8 degrees when we wonder if something could not already be done. Otherwise we can wait until April. I have the feeling the main contractor feels no pressure and prefers to work by the book, i.e. waiting for spring.



That may be true, however he is also responsible for material orders, so he does sit partially in the office. It is very annoying anyway, as in the end you have nothing in writing, and the oral communication has a rather non-binding character (perhaps that is exactly the intention).

Corona quarantine, "more expensive" projects, can all be reasons but no consolation, as the commitment interest is pushing down and we have total uncertainty about when it will continue.

From experience, I can only advise everyone now to negotiate a construction start into the contract. The idea of a deadline from the building permit is good. Legally, there must be a completion deadline, but if no construction start is fixed, you may wait until it suits the main contractor. However, we had discussed the topic before signing the contract, but were firmly blocked with the argument that there are too many unknowns and no one can know when all conditions for the start exist. Our mistake that we trusted and still signed like that.
 

ypg

2021-01-23 22:26:46
  • #4

Does this have anything to do with it? Basically, it is always annoying when the other person's schedule lags behind.
 

Robbs84

2021-01-23 22:41:38
  • #5


For that, we have now found a solution with the GÜ to start the work simultaneously. Nothing has changed neither on your end nor on ours...
 

ypg

2021-01-23 22:49:51
  • #6

So you are not alone and the only ones?
 

Similar topics
31.10.2008Is a building permit also required for a carport and equipment shed?13
15.02.2011Building permit application12
29.09.2011Is construction pre-planning without signature / contract legally valid?12
27.09.2018Cost of building permit in exemption procedure, new construction11
19.03.2015Questions about the building permit21
04.07.2015House contract with financing condition, lawyer wanted10
28.11.2024Neighbor's lawsuit against approved building permit46
18.03.2016Influence of the neighbor in building permit18
04.07.2016Building without a contract - Concerns?39
16.01.2017No building permit as long as the land is not developed?10
20.08.2017Issuance of the building permit?24
19.11.2018Fixed price commitment - price increase after expiration?25
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
04.11.2019Is only part of the building permit enforceable? How long is the building permit valid?42
11.04.2020Construction law - hire a lawyer or not yet16
15.08.2021Duration until the issuance of the building permit in BW57
30.03.2022Terminate the contract with the general contractor "early"22
22.05.2022Tips for Waiting for Building Permit26
28.06.2024Building permit - is a lawyer useful?12

Oben