Tolentino
2022-02-10 10:50:56
- #1
No, what he means is that you have to remove/excavate far more than 20cm. Calculate with 1m. At the same time, you can't use all the excavated soil everywhere for piling/filling because you need load-bearing material for that. That means in the end you have 400 cubic meters lying around on the property, of which you can use, if you're lucky, 100-200 cubic meters. So plan on having to dispose of 200-300 cubic meters -> expensive, if the soil isn't absolutely great, even more expensive.