Hilaria
2012-08-09 08:44:06
- #1
Hello,
and once again we are having trouble with our earthworks contractor.
As already with the excavation, we have the same earthworks contractor (from our general contractor). He is supposed to backfill and compact.
We had no storage option for our excavation material and had to have it transported and deposited (at our own cost). Even then, the earthworks contractor's prices were > 20% higher than the local competition. We would have gladly commissioned another earthworks contractor for the transport and deposition, but this did not happen due to missed deadlines.
Now follows the second part.
Originally, the sewer work, backfilling, and compacting were planned for last Monday. For the delivery of the backfill material, we commissioned another earthworks contractor, since this time the earthworks contractor of the general contractor is 130% !!!! above the offers of other earthworks contractors.
And as expected, last Friday we were informed that due to an employee's illness, the work could not be carried out.
So we had to cancel the delivery with the other earthworks contractor. The whole week was then about a new date, and suddenly the prescribed earthworks contractor can only do it if the supplier is on vacation, namely in 3 !! weeks. *nightingale listen here footsteps*.
We are very annoyed about this approach and believe that they want to "force" us to buy the material from this prescribed earthworks contractor. The structural builder (also prescribed by the general contractor) would have gladly taken over the work, but the general contractor refuses ...
We consider the earthworks contractor's offer not only unprofessional, no, we even consider it immoral, because they are deliberately exploiting our situation. (§ 138 Baugesetzbuch Sittenwidriges Rechtsgeschäft; Wucher)
Now we would like to hear opinions on how we should best behave or a tip on how we can still reach an amicable agreement here without much stress.
Does anyone have an idea?
Thanks
Hilaria
and once again we are having trouble with our earthworks contractor.
As already with the excavation, we have the same earthworks contractor (from our general contractor). He is supposed to backfill and compact.
We had no storage option for our excavation material and had to have it transported and deposited (at our own cost). Even then, the earthworks contractor's prices were > 20% higher than the local competition. We would have gladly commissioned another earthworks contractor for the transport and deposition, but this did not happen due to missed deadlines.
Now follows the second part.
Originally, the sewer work, backfilling, and compacting were planned for last Monday. For the delivery of the backfill material, we commissioned another earthworks contractor, since this time the earthworks contractor of the general contractor is 130% !!!! above the offers of other earthworks contractors.
And as expected, last Friday we were informed that due to an employee's illness, the work could not be carried out.
So we had to cancel the delivery with the other earthworks contractor. The whole week was then about a new date, and suddenly the prescribed earthworks contractor can only do it if the supplier is on vacation, namely in 3 !! weeks. *nightingale listen here footsteps*.
We are very annoyed about this approach and believe that they want to "force" us to buy the material from this prescribed earthworks contractor. The structural builder (also prescribed by the general contractor) would have gladly taken over the work, but the general contractor refuses ...
We consider the earthworks contractor's offer not only unprofessional, no, we even consider it immoral, because they are deliberately exploiting our situation. (§ 138 Baugesetzbuch Sittenwidriges Rechtsgeschäft; Wucher)
Now we would like to hear opinions on how we should best behave or a tip on how we can still reach an amicable agreement here without much stress.
Does anyone have an idea?
Thanks
Hilaria