I have no expert report...
 

ypg

2019-06-02 22:58:30
  • #2
That's bad. If your house should later settle, everyone will just shake their heads and offer no warranty because the builder did not provide them with the basis.
 

Freistoß88

2019-06-02 23:07:10
  • #3
I have. I sent the report on the construction area to the civil engineer... a core drilling was carried out about 20 meters from my property. Here are the results
 

M4rvin

2019-06-03 07:17:57
  • #4
Does your civil engineer also take over the warranty without an expert report? We had to commission one, otherwise they wouldn't have done anything at all... Better have your contract read through again.
 

Lumpi_LE

2019-06-03 08:31:17
  • #5
Building ground is the builder's risk; without an expert report, he can later attribute any damage to the building ground.
 

Zaba12

2019-06-03 08:55:42
  • #6
As already mentioned, if you have not conducted a soil survey on your property, you will have very, very bad chances if your house settles. A soil survey carried out 20 meters away does not interest anyone in court (if it comes to that).

Did YOU not know that a soil survey is sensible?
My shell constructor also didn’t want to do one! I didn’t care, I did it anyway. Better safe than sorry! Because after that, he can’t make excuses anymore.

Suddenly, it was no longer founded on gravel but on a clean layer of concrete.
 

Similar topics
17.04.2016Value of land and bungalow B5511
08.11.2010Offer for a semi-detached house with land, okay?11
07.07.2011Financing land now, house in 6 months?17
14.08.2012Build a home? Land in prospect19
25.03.2012Land now - house construction next year23
09.10.2012Is a soil investigation report included in prefab house construction?10
29.10.2013Property reserved, construction financing plan, architect/building permit application21
26.05.2015Buy property or leave it?12
28.07.2015Site investigation report not correct - and now?10
15.08.2016Civil engineer contradicts structural engineer27
31.07.2019Filling and compacting the ground for the house155
07.09.2021Floor plan tube house L-shape triangular plot including oak tree529
10.03.2019Purchased land after demolition, construction debris in the ground34
06.07.2021Install drainage on the property18
15.05.2019Are the house connections already one meter on the property?16
04.06.2020Civil engineer proposes deviations from the drainage plan10
29.10.2020When is land development? Before construction road or after removal51
15.01.2021Development costs for a plot in the second row35
12.05.2021Property on a slope, is the purchase worthwhile?29
14.09.2021Civil engineer calculates excavator performance by tons - experiences?21

Oben