Amount of advance payments

  • Erstellt am 2017-06-02 22:51:01

Knallkörper

2017-06-03 10:59:43
  • #1
The final installment would be far too low for me. Based on all the experience I have gathered privately and professionally in construction, I would agree to no less than a 10% final installment. If, at acceptance, a few significant or many small defects should be found, 4% is too little.
 

Nordlys

2017-06-03 11:17:33
  • #2
Nobody does that. Karsten
 

Knallkörper

2017-06-03 11:20:13
  • #3


I cannot confirm that, on the contrary. We even negotiated down to 16%, all local providers went down to 10%.
 

Nordlys

2017-06-03 11:48:14
  • #4
Ok. I wouldn't have thought that. Karsten
 

11ant

2017-06-03 12:52:30
  • #5

Yes, that's what I wrote, the contractor is covered during the entire period. Without a completion guarantee (which you don’t get for free), there remains a risk for the client – this risk lies entirely with them for the respective section already started.

But reading between the lines, the negotiation result is actually already there: namely to work through the plan unchanged from item 2 to item 8, and to shift the 5 percentage points from item 1 to item 9.

By the way, complaints about defects are not to be shifted along with this: that only applies in the case of a developer house, where you are not allowed to roam the construction site before handover of the keys. A payment plan like this usually involves partial acceptance of the trades completed up to that point, and the claiming of already identifiable need for rework. In this respect, the four percentage points for the "front door" no longer need to secure a retention for a too low-built basement.
 

Alexa2017

2017-06-04 16:01:18
  • #6
Thank you very much for the interesting answers. That also corresponds more to my not so good gut feeling. I would like to add something - what gives me even more cause for concern. The contract states: "Die Bauzeit (von Baubeginn bis Bezugsfertigkeit) beträgt 10 Monate, vorbehaltlich witterungsbedingter Ausfalltage. Der v. g. Preis gilt als verbindlicher Festpreis für die gesamte Bauzeit, längstens doch für 18 Monate nach Vertragsabschluss. Beträgt die Bauzeit aus vom AN nicht zu vertretenen Umständen mehr als 18 Monate, gerechnet ab Vertragsabschluss, so kann der AN vom AG eine angemessene Entschädigung für die eingetretenen und nachgewiesenen Kostensteigerungen gemäß §642 Baugesetzbuch verlangen." A fixed completion date is not specified.
 

Similar topics
27.07.2013Average construction time for a semi-detached house with a basement11
18.03.2015Developer information varies. What is the realistic construction time?19
08.06.2015Contract performance bond combined with final installment15
14.08.2015Inspection of detailed drawings before signing the contract for house purchase15
02.06.2016Necessary insurances during construction and afterwards11
23.01.2017What to do if the construction time is not met15
17.02.2017Payment of the final installment after assurance of defect rectification10
09.07.2021Is the construction time specified in the prefabricated house contract binding?19
06.06.2023Estimation of construction time for the new build of a semi-detached house17

Oben