Additional cost due to tile size?

  • Erstellt am 2011-07-07 13:45:16

DIERA

2013-06-24 13:32:24
  • #1
I, also as a layperson, see it exactly the same way. What do the "experienced" people here in the forum say?
 

Bauexperte

2013-06-24 14:57:51
  • #2
Hello,


It is likely to be difficult to convince the BU – despite the notarized contract – to pay the additional costs out of their margin.

"Additional costs for installation starting from the size 33x60 cm." – This tile size does not exist; it is therefore – even for the layman – obvious that this is a typo. Should the case go to court, a settlement would certainly be reached, but – in doing so both parties lose and only the lawyers win.

Try to reach an agreement with your BU about a small concession on their part given this prospect; that would be the most cost-effective solution for all involved.

I am wondering how you would react if it were the other way around. Suppose you had unfortunately transposed a number to your disadvantage ... and your BU insisted on validity.

Addendum:

Musketier is right; thanks for your hint. My above post => this tile size does not exist <= must therefore correctly read "this tile size is generally not available in the common BB."

Rhenish regards
 

Musketier

2013-06-24 16:27:37
  • #3


The question is, what was meant? You are surely assuming 33x33. But it could just as well have been 30x60 or 33x66.
By the way, there are also 33x60 cm tiles. So why should the client become suspicious?
 

Bauexperte

2013-06-24 16:50:25
  • #4
Hello Musketeer,


Mpfm - I really didn’t expect that comment from you

You know, I admit I’m annoyed that a simple typo immediately brings such a scenario to life; yes, even if it doesn’t affect me. People make mistakes; generally, they learn from them and develop further. "All" people!

In the vast majority of the BB, 30 x 60 tiles, if at all, are listed – usually in smaller standard sizes; by now, I know enough of them. From this, I can deduce that it must be a typo (which was suspected by the OP as well) and in the first step, it should probably be clarified where this error occurred; in the construction manager’s office or at the notary?

Either way, an unpleasant spectacle if the OP insists on his opinion that the construction manager must bear the extra costs. Moreover, his relationship with his construction manager will certainly not improve because of this – and that is as certain as Amen in church – there will also be situations where the OP will depend on the well-being of his construction manager.

So, why not see it as it is? A mistake was made … unfortunate, it would have been nice, but it was not meant to be … but that happens in the heat of the moment … Nobody can walk on water. Such an approach would move the OP forward if the pendulum then swings for real to the other side, because his construction manager will remember.

Rhenish greetings
 

Musketier

2013-06-24 17:49:19
  • #5


It was merely the indication that the client does not have to become suspicious based on the measurements alone. At the time of signing the contract, I had only dealt to a limited extent with actual tile sizes. So, based on the dimensions, I wouldn’t have noticed it either. However, we compared the preliminary BB (based on which we chose the construction company) 1:1 with the BB that then became part of the contract. Maybe then I would have noticed it.

I also didn’t say that one should insist on it at all costs. Especially if you want to continue building with the company. If I were in that situation, I would make my decision dependent on how the previous relationship with the construction company has been. If I have been very satisfied with everything so far, I would accommodate the company and cover the amount. Alternatively, a compromise proposal could be made that both parties can live with. If the relationship between client and construction company is already broken and ends up in court because the house is riddled with defects, then I would keep the option open to oppose it.
 

ypg

2013-06-24 18:46:21
  • #6


Interesting discussion
Interesting measurements
So what error is likely here if most construction descriptions include 30 x 30 or 30 x 60?
Rather that a number is (by accident) duplicated than that a fictitious number (here: the number 6) is used. So I would assume 30 x 60 to be meant and would argue that way to the tiler as well.
Of course, it also depends on the difference amount to be paid. If you consider why larger tile sizes involve higher installation effort, a 30 x 60 tile should not be much extra effort.
 

Similar topics
24.07.2013Additional costs due to underfloor heating11
15.03.2015Additional costs for dormer / gable or Frisian gable10
03.12.2019Additional costs due to incorrectly planned ventilation system + floor-to-ceiling windows?50
27.11.2017Are additional costs for wood-look floor tiles normal?25
22.06.2018Unauthorized high-quality work - additional costs25
03.06.2018Liability issue regarding additional costs of a planning favor12
15.09.2023Heilbronn surrounding area - experiences with local construction companies26
20.03.2020Construction company halts work despite overpayment718
14.11.2019Construction contract additional costs foundation reinforcement?10
04.12.2019Are the additional costs for lime plaster instead of gypsum plaster realistic?16
18.04.2020Additional costs for sloped land with tree coverage42
30.05.2020Support hanging and filling - Additional costs?31
23.01.2021Laying tiles additional costs55
24.01.2021Additional costs for oak stair covering instead of beech – usury?16
21.05.2021Expired fixed price guarantee - additional costs29
09.07.2021First alleged fixed price and now additional costs - legal?79
29.03.2022Single-family house KfW55 - Extra costs: rip-off or justified?29
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
05.03.2023Building in existing structures - Subsequent additional costs despite a fixed price57
12.09.2023Tile installation with additional costs for large format11

Oben