after the first days of normal shock ventilation and surface drying, in the height of summer we just left the windows tilted open. hot + tilted = constant air exchange. and yes I know, it's not cool because of possible cracks in the screed. construction was bone dry, it took about a week longer than originally thought until the readiness for tiling was ensured. since everything is still hanging/sticking to the walls/floors, everything seems to be fine.

The construction power supply is provided by your building electrician and cost us €150 including rental for the box and registration of the meter with the public utility company. Construction water was included in the total price without a meter.
 

Sebastian79

2016-05-25 11:00:52
  • #2
It is so different - RWE charges 450 euros here for the construction power connection - plus the construction power box, which my roofer wanted to set up for almost 700 euros.

I bought a box myself and connected it in the neighbor's basement - so I only had the costs for the electricity itself.
 

Sascha aus H

2016-05-25 11:06:56
  • #3

You have already answered that yourselves
Of course, I meant the construction site power meter, the installation of the connection on the property, ...
 

ONeill

2016-05-25 11:12:54
  • #4


And about the box. How expensive is such a construction power box?
 

Sebastian79

2016-05-25 11:19:27
  • #5
Nope, the box is basically free because you can sell something like that again for at least the same price.

Depending on the equipment, you have to pay between 200-500 euros. It is important to know beforehand whether an all-current sensitive fuse has to be installed ([Rohbauer fragen]).
 

DG

2016-05-25 13:17:02
  • #6
Regarding "surveying costs," one must see what is required, usually

1. Plot division: approx. 2-3k€
These costs do not apply if you purchase a fully surveyed parcel with a parcel number (!). When buying
a still to be surveyed partial area (!), these costs still apply and can vary greatly depending on the case.
2. Fine staking out (can be included in the scope of services of the shell builder/GC): approx. 500€
3. Building measurement for the cadastre: approx. 750-1000€, varies by federal state

Best regards
Dirk Grafe
 

Similar topics
02.01.2015No construction power box, take electricity from the neighbor18
04.04.2016Heat pump on separate meter or together with household electricity20
10.07.2018Does the structural builder have to paint the transition between styrofoam and brick wall black?12
15.10.2018Is the shell construction overloaded? Current situation in the construction industry!13
08.11.2018Structural shell / Structural shell cost calculation - How does it calculate?52
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
06.10.2021Photovoltaic system / heat pump, do you have 2 meters?55
14.06.2021Separate meter and electricity tariff for air-to-water heat pump sensible?103
03.07.2021Separate water meter for garden water - How to read the meter21
13.11.2021Requirements for ancillary apartment, wiring, meters, etc.13
08.10.2022Requirements for construction power box Construction power distributor12
14.06.2023Heat pump and household electricity all through one meter25
25.09.2023The supplier has incorrect meter numbers in the system - what to do?42
31.10.2023Extra meter for heat flow tariff (heating electricity tariff) yes/no?36
02.10.2024Photovoltaic - Position on the roof and only one meter?10
07.01.2025Is a heat pump meter sensible? According to the bill, yes, but is that correct?13

Oben