Zaba12
2017-09-05 08:09:54
- #1
Hello everyone,
From a financial planning perspective, I have a few thoughts and would like to hear your opinions.
Framework data:
1. The plot of land from the municipality (will be fully developed) is financed and will be paid off by the end of the year. The municipality still has to complete the development and carry out the land surveying (paid by the municipality).
2. The architect has completed the draft planning.
3. The plan is to first build an extended shell (i.e., civil engineering, drainage, shell construction, roof).
4. Afterwards, expansion will be done with known craftsmen.
Points 1-2 are paid out of "own" pocket. Points 3-4 through the house financing, which is supposed to be completed at the beginning of January. Logically, there are still a few points missing between 2 and 3.
From my point of view, these would be the points below that on the one hand make the house financing ready for disbursement (and the shell builder can start building. I hope my assumptions are correct, because without house financing ready for disbursement, a shell construction would not exist ;-).
- Building surveying, €1000
- Building permit via exemption, €1000
- Additional payment for floor area, €300
- Second notary costs (new land register costs due to house financing), €2500 (essential for the loan from my perspective, as without land registration, the bank financing the house does not provide any money)
- Builder’s liability insurance, paid
- Construction insurance / builder’s risk insurance, €400
- Soil survey, €1000
- Energy consulting (probably not the full amount at the first step), €3500
- Provision of construction electricity/water, €700
So, based on my estimate, I would end up somewhere around €10-11k that I would still have to pay out of pocket until the next invoices are paid via the house financing, correct?
Are there still any points missing or are my estimates too low?
From a financial planning perspective, I have a few thoughts and would like to hear your opinions.
Framework data:
1. The plot of land from the municipality (will be fully developed) is financed and will be paid off by the end of the year. The municipality still has to complete the development and carry out the land surveying (paid by the municipality).
2. The architect has completed the draft planning.
3. The plan is to first build an extended shell (i.e., civil engineering, drainage, shell construction, roof).
4. Afterwards, expansion will be done with known craftsmen.
Points 1-2 are paid out of "own" pocket. Points 3-4 through the house financing, which is supposed to be completed at the beginning of January. Logically, there are still a few points missing between 2 and 3.
From my point of view, these would be the points below that on the one hand make the house financing ready for disbursement (and the shell builder can start building. I hope my assumptions are correct, because without house financing ready for disbursement, a shell construction would not exist ;-).
- Building surveying, €1000
- Building permit via exemption, €1000
- Additional payment for floor area, €300
- Second notary costs (new land register costs due to house financing), €2500 (essential for the loan from my perspective, as without land registration, the bank financing the house does not provide any money)
- Builder’s liability insurance, paid
- Construction insurance / builder’s risk insurance, €400
- Soil survey, €1000
- Energy consulting (probably not the full amount at the first step), €3500
- Provision of construction electricity/water, €700
So, based on my estimate, I would end up somewhere around €10-11k that I would still have to pay out of pocket until the next invoices are paid via the house financing, correct?
Are there still any points missing or are my estimates too low?