Which tasks must be completed before signing the shell construction contract?

  • Erstellt am 2017-09-05 08:09:54

Zaba12

2017-09-05 08:09:54
  • #1
Hello everyone,

From a financial planning perspective, I have a few thoughts and would like to hear your opinions.

Framework data:
1. The plot of land from the municipality (will be fully developed) is financed and will be paid off by the end of the year. The municipality still has to complete the development and carry out the land surveying (paid by the municipality).
2. The architect has completed the draft planning.
3. The plan is to first build an extended shell (i.e., civil engineering, drainage, shell construction, roof).
4. Afterwards, expansion will be done with known craftsmen.

Points 1-2 are paid out of "own" pocket. Points 3-4 through the house financing, which is supposed to be completed at the beginning of January. Logically, there are still a few points missing between 2 and 3.

From my point of view, these would be the points below that on the one hand make the house financing ready for disbursement (and the shell builder can start building. I hope my assumptions are correct, because without house financing ready for disbursement, a shell construction would not exist ;-).

- Building surveying, €1000
- Building permit via exemption, €1000
- Additional payment for floor area, €300
- Second notary costs (new land register costs due to house financing), €2500 (essential for the loan from my perspective, as without land registration, the bank financing the house does not provide any money)
- Builder’s liability insurance, paid
- Construction insurance / builder’s risk insurance, €400
- Soil survey, €1000
- Energy consulting (probably not the full amount at the first step), €3500
- Provision of construction electricity/water, €700

So, based on my estimate, I would end up somewhere around €10-11k that I would still have to pay out of pocket until the next invoices are paid via the house financing, correct?

Are there still any points missing or are my estimates too low?
 

Zaba12

2017-09-06 10:13:26
  • #2
No one has an idea? :-)
 

ypg

2017-09-06 10:48:07
  • #3
The electricity or water company wanted the connection fees to be paid in advance.

That was almost €2000.

So just check whether it is the same with you.
 

Zaba12

2017-09-06 10:57:47
  • #4
I also roughly calculated with €2000. Seriously, they want the amount before the excavation work begins?

So another question arises? When did you submit the applications for the house connections?
 

Curly

2017-09-06 12:45:23
  • #5


When the foundation slab was poured, we took care of the house connections. However, we already received an invoice for the house connections from the waterworks 4 months before the house construction started.

Best regards
Sabine
 

Nordlys

2017-09-06 13:02:59
  • #6
Sabine, don’t confuse that. Before construction began, we received an invoice from our water supplier for the development contribution. That means every property that will be connected also participates in the costs of the piping throughout the entire area, and with that you pay for the right to connect to the wastewater and rainwater network; our contractor handled the connection for 3000 gross. After applying for connection to water and possibly gas, which should be done about six weeks before the desired date, the final invoice arrives, which includes what was done in meters from the property boundary to the house entry. This amounts here to around 3000 gross for gas and water. Karsten
 

Similar topics
14.11.2011Shell construction still this year15
19.06.2012Risk house financing or not?39
16.02.2015Property purchased - Is financing/loan for house possible?13
04.03.2015Budget plot and building with basement21
15.06.2015Property and additional costs - is the construction sum realistic?16
07.05.2016Buying a shell construction - Experiences21
30.08.2017Land charge - Separate financing for land and house12
28.01.2018Construction obligation by bank or municipality? Land purchase contract15
28.09.2019Planning our home financing34
27.08.2018New building shell construction selection: Choose a company or architects?52
09.10.2018Costs for shell construction and roof covering/insulation - fixed price offer okay?25
14.07.2019Costs for the shell construction of an office building16
22.12.2019Crane from the neighbor on my property67
11.11.2019House connections for pipe handle property10
13.06.2022Should the land be filled up or not?87
07.09.2020Application phase land - How do I finance everything?25
01.05.2021Property with expansion house experiences14
21.07.2021Planned financing land + single-family house 2022/2023 - Are the framework conditions suitable?28
05.09.2022Buy the plot separately or finance it together?15
14.03.2023Finance buying land or rather leave it?60

Oben