What costs can we expect?

  • Erstellt am 2010-07-04 11:51:09

misscaro

2010-07-23 23:09:36
  • #1
so you can add 30,000,- for incidental construction costs and about 15,000,- for floor and wall coverings, each additional socket costs extra. If your plot is not properly conditioned, there will be additional costs. The outdoor facilities? Kitchen?

You add that up and suddenly you are also at 280,000-300,000,-

Regards Caro
 

Uhu-Schuhu

2010-10-16 00:01:31
  • #2
Hello everyone,
I find this thread quite interesting
The land costs differ significantly. Here, the price per square meter of building land is 300 euros.
I would be interested to know if the house construction costs also vary that much.
Are there people from the Stuttgart metropolitan area here who could also say something about the total costs of their house?
 

Undercover

2010-11-20 18:10:01
  • #3
Boy oh boy oh boy you guys have some crazy numbers

So here are my numbers

10000 euros: Notary, surveying; soil sample, taxes.

4000 euros house connections (without gas)

120000 the house 113 sqm living space on 2 floors
without basement but 30 sqm attic expandable
Kfw 70 with thermal slab
triple glazing
140 exterior insulation
air heat pump
turnkey

15500 carport, paving, terrace, garden, tiles, paint

30500 for the plot 1100 sqm <-- bargain :P

180000 euros

Ok ok now probably 90% are saying that’s no wonder with almost 30000 plot price

Best regards Undercover
 

giftmischer

2010-11-21 07:41:10
  • #4
We have really compared several offers by now. Sometimes this was missing, sometimes that. But one thing was the same in all of them. Until you move in, you can expect around €1,300 - €1,500/m² of living space. On top of that comes all the bureaucratic stuff.

Furthermore, some details are missing to truly compare the prices:
What type of heating?
Roller shutters (possibly electric?)
Is a significant amount of flooring already installed by the builder (for turnkey), or do you have to do everything yourself? Depending on the quality, you can easily add another €25-30/m² just for materials.
....
 

Undercover

2010-11-21 17:26:17
  • #5
The two bathrooms are included (tile walls + floor)

Heating is from: Vaillant air-water heat pump geoTHERM VWL 62/3 S

Roller shutters with plastic slats (I have already had the wiring installed, I am retrofitting the motors myself)

Best regards
 

Chemi

2011-01-31 08:44:05
  • #6


Which construction company did you use for the house?
 

Similar topics
14.08.2012Build a home? Land in prospect19
25.03.2012Land now - house construction next year23
02.09.2013Angular bungalow on 800m² plot - financially feasible?16
27.02.2013Turnkey prefabricated house - total price okay?59
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
22.08.2013Plot - Decision?14
14.01.2014Buy land let build dream house26
14.07.2015Turnkey home. Free land17
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
02.03.2015Turnkey house construction, but with own room layout?17
01.04.2015Land is available - prerequisite to build 2.5 stories!16
31.03.2015Property / Financing amount / Insurance? Experiences10
13.03.2018Turnkey Construction Land and Prices79
08.08.2017Buy land with cash? How to build financing?44
25.02.2017Price for 1 sqm turnkey?11
29.08.2019Loan amount in Berlin with existing land14
24.11.2017Consultation and opinions on the property32
12.05.2022Is the budget for a prefab house (turnkey) realistic?15