Hello dear community,

my shell construction is complete. Next week the roof truss is supposed to be installed and then the roof will be covered. My builder says he wants to install the windows only after that. Does that make sense? I have concerns, as nothing will happen for 4 weeks except the roof. In my opinion, the interior work could take place in parallel. It is a 4-unit house, about 16x16m and two full stories.
As a reason, he says he doesn't want the windows to get damaged if something falls during the roofing work.
What do you think about it?
Best regards
Tommy
 

K1300S

2021-10-20 08:47:52
  • #2
The interior work should only start when the house is "sealed" - that is, when the windows are in *and* the roof is on. Depending on what is being done (drywall?), otherwise it can really cause problems.

Apart from that: Are you having the entire house built? Otherwise, the developer will (really?) probably not change their way of working just because of a single apartment buyer.
 

RotorMotor

2021-10-20 08:51:49
  • #3
It would also be very unusual if he already has the windows immediately after the shell construction. Normally, they are only measured and manufactured afterward. If it currently only takes 4 weeks there, everything has gone very well.
 

Der_Tommy

2021-10-20 08:55:04
  • #4
I am having the house built by the developer and renting out all the apartments. What can be done in parallel to the roofing?
 

K1300S

2021-10-20 08:59:04
  • #5
Waiting? ;) Otherwise, sampling equipment, applying for house connections, ... at most maybe preparing electrical/plumbing installation (milling slots).
 

konibar

2021-10-20 09:14:39
  • #6
I would rather assume that windows with standard dimensions are used and thus are stock items. Custom-made individual production is simply too expensive nowadays.
 

Similar topics
14.11.2011Shell construction still this year15
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
25.05.2015Extractor hood / roof or wall14
01.03.2015The developer does not build according to the plan14
27.02.2015Purchase shell construction and complete it including financing15
26.04.2015Construction start in winter? Begin next spring because of moisture?16
13.06.2015New construction with developer / construction drawing documents23
07.05.2016Buying a shell construction - Experiences21
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
14.11.2016Soundproofing - weakest link? (Windows?)26
22.05.2017Almost every window has scratches - what is considered normal?22
20.10.2017Roof with photovoltaic or other investment, any experiences?19
19.02.2022Anthracite windows - Which roof color63
29.01.2018Windows on the roof terrace are installed "strangely".21
03.06.2020Floor-to-ceiling windows - Why floor-to-ceiling windows? Advantages and disadvantages?112
02.07.2019Purlin distance from exterior wall or roof16
11.08.2019Installing raffstores in the shell construction prepared for blinds15
27.10.2019Water in the inner frame: Shoddy construction? (Shell construction)15
28.03.2024Offer for shell construction of a single-family house 170 sqm - Is the price market-appropriate?57

Oben