Piotr1981
2020-07-20 20:09:57
- #1
Hi everyone,
The shell construction including the brickwork will be completed at the end of August. To gain some time towards the end, I would be interested to know if and what you have planned/carried out in terms of the sequence of trades.
The carpenter and roofer are practically ready and would start immediately after the shell construction, but in parallel I would already have the measurements of the windows taken (windows have a delivery time of about 3 weeks). For example, what would you have done or planned during the delivery time of the windows so that I can gain some time towards the end?
The same applies later during the drying phase of the screed.
Looking forward to your ideas/inspirations.
Best regards & thanks Piotr
The shell construction including the brickwork will be completed at the end of August. To gain some time towards the end, I would be interested to know if and what you have planned/carried out in terms of the sequence of trades.
The carpenter and roofer are practically ready and would start immediately after the shell construction, but in parallel I would already have the measurements of the windows taken (windows have a delivery time of about 3 weeks). For example, what would you have done or planned during the delivery time of the windows so that I can gain some time towards the end?
The same applies later during the drying phase of the screed.
Looking forward to your ideas/inspirations.
Best regards & thanks Piotr