The structural construction company cancels one day after the excavation work began!

  • Erstellt am 2018-02-06 11:17:36

ensi1981

2018-02-08 06:11:56
  • #1
Now a letter from the company has arrived. They write that they have no time for the construction project and that we do not even have a legally binding contract.

I think this is really helpful now :)
 

toxicmolotof

2018-02-08 07:08:14
  • #2
Then it is now up to you (and a specialist lawyer) to prove the opposite and, if applicable, to claim damages.

However, before that, (if a contractual relationship actually exists) the formally correct procedure must be followed, i.e., setting a default, etc... but your lawyer will handle that for you.

In the meantime, have your architect call around for a new shell builder.

Speaking of the architect... what does he say about it? Isn't his job to coordinate the trades and ensure safety in the planning?
 

ensi1981

2018-02-08 07:18:15
  • #3
The architect was of course really uncomfortable about it. So was the civil engineer ... he recommended the shell builder to us back then.

My architect arranged a new shell builder on the very same day. He was actually the first choice at the time but had withdrawn his offer due to lack of time. Thanks to the excellent winter so far, he now has capacity and can start in 3 weeks. He stands by his previous offer and continues to offer me a written contract for work to calm my nerves and because he considers the way his predecessor acted a disgrace in his industry.
 

Joedreck

2018-02-08 08:39:39
  • #4
In my humble opinion, I advise you to let it go. It is of course annoying and the old company is stupid, but you are lucky and have your peace...
 

ruppsn

2018-02-08 08:57:39
  • #5
So? Will you conclude a contract for work and services with the new shell construction contractor? [emoji6]
 

ruppsn

2018-02-08 09:15:39
  • #6
Nobody is saying otherwise. [emoji4] I just wonder why expose yourself to the risk of later finding it significantly harder to prove that you accepted a specific offer? It doesn't even take 5 minutes. "I hereby accept the offer dated ... in the version ... under the conditions stated therein. Please confirm briefly." You wouldn't even need the last sentence. But to each their own risk tolerance and taste. I just find it negligent, especially with amounts like these, not to do so... What industry are you actually in? I ask because in my professional life, I've never experienced with any employer that such contract sums were approved without a written contract. On the contrary: usually, lawyers first draft a contract... so it would be interesting to know in which industry such amounts are approved verbally and with a handshake...
 

Similar topics
23.10.2008We need an architect - or should I do it myself?14
02.01.2009Experiences with architects15
19.03.2013Turnkey or build with architects?19
21.07.2013Cost estimates from two architects differ greatly!10
13.11.2013Do you absolutely need an architect?10
16.12.2013Pre-planning with the architect - is having your own floor plan sensible?18
30.01.2014Architect's cost estimation15
28.04.2014Cost estimate - contract for work16
21.08.2014Construction costs when building with architects. What does your experience say?18
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
19.12.2014Finding architects - but how?26
08.09.2015Massive house by the architect, approximate costs?16
23.09.2015Responsibilities of the Architect in Tendering18
29.10.2015Is it normal for the purchase of land to be tied to an architect?16
19.01.2016Construction project with architects31
20.08.2016Should the house be planned by a general contractor or architects?30
29.01.2019Responsibility of the architect in case of KfW interest and further matters148
27.08.2018New building shell construction selection: Choose a company or architects?52
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
25.06.2022Is the cost estimation by the architect realistic?39

Oben