Fenix2k
2016-10-05 19:57:47
- #1
Hello everyone,
After intensive consideration of all personal pros and cons, we decided about 3 weeks before the groundbreaking to cancel our house building project.
(We are aware that this decision came too late, but better than if the house is finished and the realization comes too late... in any case, after several weeks we still feel very good and relieved with this decision)
We signed an "architect and project management contract" with a so-called construction supervisor. The contract includes the construction description at an agreed fixed price of €321,000.
The fee for the construction supervisor is (unfortunately) not itemized.
The following service levels are listed:
- Construction planning / consulting
- Awarding of construction contracts
- Construction management until handover of keys
- Support for warranty claims...
Under § Termination it only states:
This contract can be terminated by both contracting parties only for an important reason.
There is nothing in the contract about possible cancellation costs.
The service of the civil engineer (preparation of building application documents, structural calculation, thermal insulation certificate) we paid separately (€2,169), so it is not included in the construction supervisor’s service!
The construction supervisor is now issuing us a final invoice:
Costs for sales: 2% + costs for services provided in tenders 1.5% of the contract sum = €11,242
- What does "sales" mean in this context?
- Is it common to calculate here with flat percentages?
- So far, at most earthworks and shell construction could have been tendered.
Of the €11,242, we have already paid €2,425 for stage 1 (construction planning/consulting).
Now we are being asked to pay the remaining €8,742, which I consider inappropriate in relation to stage 1 and the civil engineer’s service...
What do you think? Do we have to pay this "lesson money" to this extent or do we have any means to oppose it?
Thanks and regards,
Fenix
After intensive consideration of all personal pros and cons, we decided about 3 weeks before the groundbreaking to cancel our house building project.
(We are aware that this decision came too late, but better than if the house is finished and the realization comes too late... in any case, after several weeks we still feel very good and relieved with this decision)
We signed an "architect and project management contract" with a so-called construction supervisor. The contract includes the construction description at an agreed fixed price of €321,000.
The fee for the construction supervisor is (unfortunately) not itemized.
The following service levels are listed:
- Construction planning / consulting
- Awarding of construction contracts
- Construction management until handover of keys
- Support for warranty claims...
Under § Termination it only states:
This contract can be terminated by both contracting parties only for an important reason.
There is nothing in the contract about possible cancellation costs.
The service of the civil engineer (preparation of building application documents, structural calculation, thermal insulation certificate) we paid separately (€2,169), so it is not included in the construction supervisor’s service!
The construction supervisor is now issuing us a final invoice:
Costs for sales: 2% + costs for services provided in tenders 1.5% of the contract sum = €11,242
- What does "sales" mean in this context?
- Is it common to calculate here with flat percentages?
- So far, at most earthworks and shell construction could have been tendered.
Of the €11,242, we have already paid €2,425 for stage 1 (construction planning/consulting).
Now we are being asked to pay the remaining €8,742, which I consider inappropriate in relation to stage 1 and the civil engineer’s service...
What do you think? Do we have to pay this "lesson money" to this extent or do we have any means to oppose it?
Thanks and regards,
Fenix