ChrisEF
2018-01-12 08:55:16
- #1
Hello everyone,
our home construction company has been planning our single-family house since March 2017. We received the building permit in November, and subsequently the drainage planning was created and submitted to the local drainage authority (mid-December 2017).
Now we have received feedback that we can expect a processing time of 8 to 12 weeks. For ultimately 3 pages...
1st question: Could our home construction company have created the building application and the drainage application simultaneously?
2nd question: Is it possible to start the house construction (excavation, building the basement, etc.) before the drainage permit is granted?
We want it to finally get started...
our home construction company has been planning our single-family house since March 2017. We received the building permit in November, and subsequently the drainage planning was created and submitted to the local drainage authority (mid-December 2017).
Now we have received feedback that we can expect a processing time of 8 to 12 weeks. For ultimately 3 pages...
1st question: Could our home construction company have created the building application and the drainage application simultaneously?
2nd question: Is it possible to start the house construction (excavation, building the basement, etc.) before the drainage permit is granted?
We want it to finally get started...