Should the screed be laid as soon as possible after pouring the base slab?

  • Erstellt am 2024-07-28 02:49:34

DEKU_1992

2024-07-28 02:49:34
  • #1
Hello everyone,

we are currently renovating the chamber where the groundwater pump is located, which supplies the house with water, and a staircase to the upper floor.

Due to massive delays caused by unforeseen structural damage (ring foundation and moisture damage), we can no longer invest much time in drying.

Therefore, my question is: How early and as quickly as possible can a floating screed be laid after pouring the floor slab?

The conditions are as follows:

It is a well-ventilated, tall, and basically well-heatable room with the dimensions 3.03 m x 1.11 m x 5.00 m. The removed floor slab is to be restored by "eating up" 10 cm of concrete, after which a floating screed is to be laid. No floor covering will be installed on it for the next few months.

Afterwards, only a welder, bricklayer, and stair builder will come to do their work. The floor does not have to bear great forces since everything above is built into the wall, but I am afraid of covering the concrete too early with screed.

Thank you very much for your answers. If you have any questions, I am happy to answer them.
 

DEKU_1992

2024-09-13 06:22:54
  • #2
It's just a theory... Somehow forums are useless.

Thank you for no comments.

Regards
 

HausKaufBayern

2024-09-13 07:13:29
  • #3
Try it in marriage "construction"-oriented forums, you'll find something there via Google
 

Buchsbaum066

2024-09-13 08:00:11
  • #4
Why do you need the screed on top of the concrete?

Then just pour the concrete and let it cure. The stair builder should be able to work with spacer blocks etc.

Otherwise, there are additives for concrete that make it dry faster. In the worst case, you won’t get the moisture out from underneath anymore. I know a builder who also didn’t let it dry enough. The tiles in the living room still get moisture spots. After 10 years. This is not a basement but an intermediate ceiling.

But giving advice here without knowing the local conditions is actually nonsense. I would give the whole thing plenty of time to dry properly.
 

nordanney

2024-09-13 08:54:04
  • #5

When it comes to strength, the "28-day" rule applies. Usually, the concrete is sufficiently cured (and sufficiently dry) by then.
Since you want to continue very quickly, I would personally start with the screed after 10 days and hope that it has dried enough by then.
 

Buchsbaum066

2024-09-13 09:25:46
  • #6


Hope dies last, as always!
 

Similar topics
05.06.2010Basement made of high perforated bricks or concrete?11
10.08.2015In which season of the year is it best to bring screed into the basement10
07.08.2016Upper floor without screed - only concrete floor15
22.12.2016Is rain harmful to concrete slabs?12
20.08.2016Base slab vs strip foundation15
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
06.10.2016Base plate with defects?22
15.03.2018When is a slope a slope? Basement vs. slab19
18.08.2017Base plate ready - construction supervisor absent20
06.10.2019Base plate with concrete core activation. What is your opinion?46
07.01.2019House with slab foundation on a slope52
09.02.2019Ground slab with strip foundation and frost skirt23
14.10.2019Dampness in the basement on the floor slab and walls25
16.04.2020Pour the ground slab in sections?19
27.05.2020Set formwork blocks on the foundation or in concrete21
30.06.2020Base plate, too little cement in the concrete19
12.11.2020Formwork blocks on the foundation slab in a mortar bed or not?13
26.02.2022Concrete floor without screed on the upper floor/attic, what to do?24
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17

Oben