Hello everyone,
I am still studying the construction service descriptions from general contractors for our construction project.
In the construction service description from our preferred partner, I find the attached drawing in the technical description of the base slab.
It states there (highlighted in color by me) that the sealing of earth-contacting parts shall/must be carried out by the builder on site. Further down in the construction service description, I find the following section:
Silly question: Is that normal? I had assumed that this was part of the scope of "building the house." Must/can I have this carried out by the landscaper as part of the garden and landscaping work?
Thanks and best regards
SoL

I am still studying the construction service descriptions from general contractors for our construction project.
In the construction service description from our preferred partner, I find the attached drawing in the technical description of the base slab.
It states there (highlighted in color by me) that the sealing of earth-contacting parts shall/must be carried out by the builder on site. Further down in the construction service description, I find the following section:
Depending on the type of landscaping work adjoining the facades of the house, it must be ensured under the responsibility of the builders that the earth-contacting surfaces of the facade are protected against ground moisture. The builder must coordinate these measures with their landscaping designer.
Silly question: Is that normal? I had assumed that this was part of the scope of "building the house." Must/can I have this carried out by the landscaper as part of the garden and landscaping work?
Thanks and best regards