Bieber0815
2016-11-02 08:42:17
- #1
Is it a shaft for 8 main lines, planned to be in a corner in the bathroom but now is right in the middle of a door? From dangerous half-knowledge, since I neither understand the planning (excerpt) nor your construction project, I would say that the proposal is rubbish. You apparently get 2 additional 90° bends in your lines each. Your site manager should have this approved by the ventilation installer to check whether pressure losses etc. are still acceptable and whether the system can still be cleaned later.