Once again, away from the doomsday mood. Some people have nothing else to do. When did you sign? Date on the contract?
 

Mikehausbau

2022-04-07 14:27:55
  • #2

At the beginning of the year, before the invasion!
 

Benutzer200

2022-04-07 14:31:46
  • #3

Do that.
But it won't help much if the company refers to Section 313. According to a relatively recent Federal Court of Justice ruling, this is a reason that allows the company to make adjustments. I strongly assume that a war with its consequences is a disruption of the basis of the business.

Below is a legal assessment from a law firm. It may also be of interest to others affected.


 

cryptoki

2022-04-07 14:31:48
  • #4
The situation was already just as unpredictable as it is today. The price level at the beginning of February was immense, the price of wood was pretty much at its peak. Steel was already expensive as well. No idea why the company should calculate such different prices today. Such steps are more understandable with contracts from 2021. I find it interesting. In the conversation, refer once to the high prices from February 2022. The price of wood has been falling for weeks. Your turnkey house including the basement is already pretty good in terms of price.
 

WilderSueden

2022-04-07 14:35:37
  • #5
But the war is not here. Basically, building materials are available, many just more expensive and some only with longer waiting times. In view of last year’s price explosions, larger price fluctuations and increases as well as delivery problems had to be expected in January as well.
 

cryptoki

2022-04-07 14:37:31
  • #6
That's exactly how it is. In this respect, I would question the move under Baugesetzbuch 313 for this young contract. A conversation with a friendly reference to the facts might bring an agreement. After that, you can always still march to a lawyer.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18
06.09.2024Contractual penalty in the Building Code contract - new construction20

Oben