Price increase after order confirmation / contract conclusion

  • Erstellt am 2021-04-10 13:53:42

ypg

2021-04-11 10:42:24
  • #1

Which trade and measurements are involved?


That could lead to, as we have read here in the forum from the Fleischerhaus: too cheap can mean insolvency of a company. Is that helpful to everyone?
The situation with building materials is probably very tense at the moment, which one should realistically consider.
I find this “sliding agreement” interesting – with it you could potentially benefit from falling prices (although that is of course not realistic).
What if he obviously miscalculated? Would you insist on paying the lower price?


One doesn’t have to start shooting sparrows right away and speak of loss of trust when one can’t even speak of a disagreement yet.
 

berny

2021-04-11 10:43:56
  • #2
@ ypg: Everyone has their own experiences after all...
 

TraumvHaus

2021-04-11 11:09:09
  • #3
It is about the roof ([Dachtuhl und Dacheindeckung]). As said, we do not yet know how high the price increase will be. Based on that, we will also make a decision. But as described, there is a signed contract. And normally all contracting parties have to adhere to it. If we were to cancel, we would also have to pay a corresponding penalty. As mentioned several times already, we are aiming for an agreement and not for conflict. Just want to know what rights we have.
 

Osnabruecker

2021-04-11 11:37:45
  • #4
As you might have noticed, wood prices have exploded by 50%, so if prices need to be increased for a trade, then in your case, it would be for the roof structure.

However, this should maybe only be €1,000 in additional material costs.

I wouldn’t jeopardize the construction site for that. I think your approach is good, wait and negotiate with him. All other new offers would also include the new material price.
 

guckuck2

2021-04-11 12:00:08
  • #5


The probability of falling prices is almost zero, and moreover, how are you supposed to prove that as a customer? In my opinion, it also contradicts the Building Code; the cost risk generally lies with the contractor.

If the roofer offers a price, then concludes the contract and does not secure the material on time (at the calculated price), that is his risk. The question is, is there a plan B that would be cheaper than plan A including an addendum? There must have been other offers, of course you can actively approach them to see if they are available and still willing to match the price.
 

Thomas911

2021-05-21 23:48:05
  • #6
I would be interested to know how you resolved the situation...was there a price increase and if so, by how much? We are currently in a similar situation
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
10.02.2020Must the construction company itemize the costs per trade?13
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
22.04.2021Costs for the heating & sanitary trade86
09.05.2021Price adjustment clause in the contract with the general contractor18

Oben