Partial payments specified in the construction contract can be changed.

  • Erstellt am 2012-01-20 13:22:08

Hilaria

2012-01-20 13:22:08
  • #1
Hello,

Actually, I thought we had finally found a "serious" general contractor for our construction project. Now I have studied the construction contract more closely and am somewhat surprised by some passages.

In general, one signs that nothing, absolutely nothing, entitles one to reduce or withhold progress payments.

Furthermore, the progress payments (in my opinion) are higher here than according to the Broker and Developer Ordinance (I thought the highest progress payment rates were regulated there).

May I submit the progress payments here and would someone say, okay, this is acceptable or no, better to avoid?

Thank you
Hilaria
 

Bauexperte

2012-01-20 14:21:33
  • #2
Hello,


Contract according to VOB?


Of course you can do that

Kind regards
 

Hilaria

2012-01-20 14:36:17
  • #3
Hello construction expert,
so the warranty is according to the Building Code, otherwise there is nothing stating what the contract is based on.

I will write the due dates here:

5% upon handing over the building application documents to the client
20% completion of the basement ceiling
10% completion of the ground floor ceiling
10% completion of the upper floor ceiling
10% roof covering
10% window installation
10% rough installation
10% interior plaster
10% screed and tiling work
3% house and interior doors
2% acceptance

What I also find missing and suspicious in the contract are points like:

1.) Securing insolvency or completion guarantee / warranty guarantee - not a word about it

2.) Completion guarantee is stated as follows: from the placement of the base slab 8 months + delays that are not the fault of the construction company,
force majeure, strike, bad weather, delayed own services, unjustified payment default...

3.) Penalty in the form of claims for damages by the
client according to the Civil Code - what does that mean in plain language, I have already searched stupidly and extensively?

General assessment, is this acceptable or not?
 

Bauexperte

2012-01-20 20:38:12
  • #4
Hello,


Better


That’s ok, maybe your seller also takes the building application to the building authority...


That makes 65% for the enclosed shell without exterior plaster; unacceptable. In the worst case, you won't get the construction finished with the remaining 35%.

[...]


Unfortunately, there is no legal obligation for this; however, you can clearly tell from that which providers are worth dealing with.


This wording is completely fine – sellers may be able to influence many things, but not force majeure or weather – with this wording, the legislator has backed the general contractor/construction company/builder.


Book 2 – Law of obligations (§§ 241 - 853), Section 1 – Content of obligations (§§ 241 - 304), Title 1 – Obligation to perform (§§ 241 - 292)

Basically, a contract according to the Building Code is always recommended; if concluded according to the VOB you cannot make reductions, let alone refuse acceptance – even in justified cases. With a contract based on the Building Code, you can terminate at any time, and you can deduct up to twice the value of any existing defects from the next partial payment. Logically, only until the defect is remedied.

However, if you sign the statement: "Generally, one signs that nothing, absolutely nothing entitles you to reduce or withhold partial payments", you override the legal provisions with your signature.

Best regards
 

Hilaria

2012-01-21 13:38:39
  • #5
Thank you, construction expert, so my impression was not entirely wrong ...

Well, the question is only, where can I find a better provider, the way here was already very difficult.

However, we will state that we do not agree with the contract as it is, let's see how the company reacts.

One more question: shouldn't the advance payments be based on the [Makler- und Bauträgerverordnung], weren't there various rulings that led to payment plans being voided or is that a "Kannbestimmung"?

Regards
Hilaria
 

Bauexperte

2012-01-21 15:50:47
  • #6
Hello,


Collateral damage unfortunately also occurs when searching for the right construction partner; don’t let it get you down!

I have found that smaller, local construction companies are always the better choice. In your area in Bavaria, there are surely plenty of them


The Broker and Developer Ordinance is - as the name suggests - mandatory *only* for developers. Due to the numerous court rulings, it will - hopefully - not take long until the Federal Court of Justice issues a binding recommendation for legislative change to the government.

Court rulings are always *only* one of many instruments and not necessarily binding for other competitors. Try your luck, maybe your favored construction company will change its payment plan; by the way, I would be interested in the BB ... usually there are causal connections to be found there.

As a rule of thumb: if the installment payments exceed 55 - 58% for a closed shell construction - shell, carpenter, roofer, window installer - stay away; even if a down payment is requested. Payments should always be made after completion of the respective work!

Good luck!
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
27.02.2015Purchase shell construction and complete it including financing15
04.07.2016Building without a contract - Concerns?39
05.10.2016Apartment sale through an agent - what to pay attention to?27
28.02.2017Are securities customary for completion and warranty?24
20.04.2017Payment plan with 35% after the shell construction, okay?10
11.12.2017Amount of advance payments16
04.05.2021Broker for owners - benefits / advantages?153
02.10.2018Negotiation strategy with the agent and the seller40
24.04.2020How do brokers negotiate the purchase price?43
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
02.09.2019Is the sample exhibition binding? Deviation from execution12
14.04.2020Security deposit according to §650 of the Building Code20
02.02.2020Payment plan (Broker and Developer Regulation) and Developer's payment plan10
11.11.2020Cancellation of a contract with a plumbing company24
13.01.2021Broker fraud or tax evasion?63
10.04.2021Delays with the general contractor, no deadline set according to § 650 Building Code65
01.07.2022Construction delay without completion. The house simply is not finished21
27.01.2024House purchase through agent, now contract terminated18

Oben