Hello everyone,
our construction is actually progressing quite well. However, I just read the point in the construction description: "All cables will be laid under plaster in conduit (not in the utility room, as it is surface-mounted)".
Since everything is monitored via the BT, but I take photos daily, I just checked again and it is clearly visible in the pictures that conduit was only used on the floor.
The electrical, satellite, and network cables were all only laid up to a certain height in the walls and then plastered over.
Now the plaster and screed are already in place, and I am wondering if they are supposed to tear everything open and redo it? I don’t want to have to break everything open later even for a single cable fault!
What can or should I do now?
Regards, Frank
our construction is actually progressing quite well. However, I just read the point in the construction description: "All cables will be laid under plaster in conduit (not in the utility room, as it is surface-mounted)".
Since everything is monitored via the BT, but I take photos daily, I just checked again and it is clearly visible in the pictures that conduit was only used on the floor.
The electrical, satellite, and network cables were all only laid up to a certain height in the walls and then plastered over.
Now the plaster and screed are already in place, and I am wondering if they are supposed to tear everything open and redo it? I don’t want to have to break everything open later even for a single cable fault!
What can or should I do now?
Regards, Frank