Main Pipeline Plan - Wastewater Drainage and Elevation Planning

  • Erstellt am 2020-09-24 19:39:46

Tolentino

2020-10-12 16:22:39
  • #1
Ah ok. Yes, that's what I thought too, but our civil engineer wants to do the pipelines only after the houses are standing. He says it doesn't make sense to do it before...
 

Nida35a

2020-10-12 16:29:10
  • #2
if he removes 30-40cm of topsoil for the construction road, he already has half the depth of the trench, and 1.5m from the fence the trench is never ever a lane. Ask him for 2 quotes, now and later
 