Light shaft planning with possible seepage water

  • Erstellt am 2017-05-06 13:14:08

V3ctra

2017-05-06 13:14:08
  • #1
Hello everyone,
We have now completed our input planning meeting. The draftsman pointed out that WU light wells may be required according to the soil investigation report. One light well including insulation is estimated to cost about €2000, and 4 units are planned.
We have already included light wells with drainage in the offer, but these are not watertight.

The report states the following:

Seepage water / accumulated seepage water / design water level

was not investigated on 10.01.2017.
The soil moisture within the soil layers explored in the boreholes can be described as dry to very moist. The occurrence of accumulated surface water on cohesive layers (e.g., silt/clay layers) as well as above the underlying rock horizon cannot be excluded.
The amount of accumulated surface water depends on previous rainfall and can be well managed during the construction period by means of surface water pumps (possibly in the form of a construction water retention system: system of drainage ditches/pipes and sump pumps).
The design water level is initially to be assumed here with a safety allowance of 1.0 m above the bottom edge of the floor slab (~1.6 m below the ground surface) based on experience with comparable soils/ground conditions. A refinement (allowance in case of indications of possible oxidation/reduction horizons, i.e. groundwater-influenced areas) can be made after inspection of the excavation base or the excavation itself. Furthermore, it is recommended to assign a gravel drainage layer around the lower third of the working space combined with a 0.20 m thick layer with capillary-breaking properties beneath the floor slab. This achieves rapid distribution of incoming water as well as regulation of local water inflows.


.....


When executed in WU concrete or as a white tank, the specifications of the WU guideline (DAfStb, 2006), DIN EN 206-1, and DIN 1045-2 apply; the standards DIN 18195-4 and 6 and VOB/C ATV 18336 do not apply according to own statements for constructions made of watertight concrete. The stress class 1 according to the WU guideline is to be assumed. The service class is to be determined by the specialist planner.

If light wells are to be executed here, they must be made pressure-water-tight or incorporated into the overall sealing concept or positioned at a corresponding height.

.....


If the light wells are now planned as high as possible, would it then be possible to use our "normal" light wells, right?
Thanks in advance for your answers.
Regards
 

RobsonMKK

2017-05-06 13:56:16
  • #2
Simply omit the basement windows entirely ;-)
 

Similar topics
05.06.2010Basement made of high perforated bricks or concrete?11
06.10.2015Correct formulation for a waterproof basement11
22.12.2016Is rain harmful to concrete slabs?12
20.08.2016Base slab vs strip foundation15
06.10.2016Base plate with defects?22
15.03.2018When is a slope a slope? Basement vs. slab19
18.08.2017Base plate ready - construction supervisor absent20
06.10.2019Base plate with concrete core activation. What is your opinion?46
18.04.2025Construction company wanted in the Stuttgart metropolitan area!212
07.01.2019House with slab foundation on a slope52
09.02.2019Ground slab with strip foundation and frost skirt23
14.10.2019Dampness in the basement on the floor slab and walls25
16.04.2020Pour the ground slab in sections?19
23.04.2020Are additives avoidable in concrete?20
27.05.2020Set formwork blocks on the foundation or in concrete21
30.06.2020Base plate, too little cement in the concrete19
11.08.2020Light shafts in waterproof basement10
12.11.2020Formwork blocks on the foundation slab in a mortar bed or not?13
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
29.02.2024Base plate with polymer fibers and less reinforcing steel23

Oben