Is the payment schedule okay? Please give your opinion.

  • Erstellt am 2020-06-03 23:44:54

Mr.Boing

2020-06-03 23:44:54
  • #1
Hello everyone,

we had an appointment last week with a developer that we liked a lot. However, the payment plan seems quite developer-friendly to me. What do you think about it?














































after completion of the building application documents 5 %
after completion of the base/foundations 19 %
after completion of ground floor masonry (without ETICS) 16 %
after completion of roof truss erection 17 %
after completion of roofer and plumber work (without downpipes and roof boxes) 9 %
after completion of window installation (without sealing and windowsills) 9 %
after completion of electrical rough-in 8 %
after completion of drywall construction 5 %
after completion of exterior plaster without base 5 %
after installation of the heating system 5 %
simultaneously upon handover of the house 2 %


Thank you very much in advance for your help
 

T_im_Norden

2020-06-04 06:36:35
  • #2
57% paid for just a roof structure I find very much
 

Mr.Boing

2020-06-04 15:13:11
  • #3
Thanks in advance. What is a normal level?
 

MaxiFrett

2020-06-04 19:37:16
  • #4
We are currently also negotiating with a general contractor. The contract contains the following data - each after ... :


















































































































Trade
Payment Total
Design planning 7% 7%
Building application or building notification 8% 15%
Basement floor slab 15% 30%
Completion of the basement concrete ceiling 8% 38%
Completion of the ground floor concrete ceiling 10% 48%
Roof frame 12% 60%
Roofing and plumbing work 5% 65%
Installation of windows and patio doors (without front door) 7% 72%
Electrical and sanitary rough installation 8% 80%
Interior plastering work 4% 84%
Screed 6% 90%
Exterior plaster 3% 93%
Start heating program / installation of ventilation system 3% 96%
Tiling (without skirting boards) 2% 98%
Handover 2% 100%
 

Tolentino

2020-06-04 22:00:54
  • #5
Mine looks like this, I signed it this way because after all 10% remain until the final acceptance:







































































Construction status Installment cum
Start planning 7% 7%
Submission of building application 5% 12%
Submission of building permit 5% 17%
Ground slab completed 10% 27%
Load-bearing walls on ground floor completed 16% 43%
Roof frame erected 8% 51%
Roof covering completed 9% 60%
Windows installed 10% 70%
Electrical and interior plaster completed 6% 76%
Heating and sanitation completed 6% 82%
Screed completed 4% 86%
Start of exterior plaster 4% 90%
Final acceptance 10% 100%
 

kati1337

2020-06-05 11:42:54
  • #6
We have:











































Share Total
Building notification & completion of base slab 15% 15%
Roof frame 30% 45%
Window installation 15% 60%
Completion of screed 20% 80%
Installation of heating system 5% 85%
Completion and acceptance 5% 90%
Completion of remaining work, handover 10% 100%


I actually find it quite okay like this.
 

Similar topics
13.03.2015Opinions on window parapet height sought30
22.04.2015Window, roller shutter, exterior plaster10
31.07.2016Electrical inspection, Q2, bathroom tiles, knee wall, floor-to-ceiling windows23
09.01.2017Interior and exterior plaster in winter10
05.01.2017Bathtub in front of the window - parapet height?14
09.08.2017Is exterior plastering possible before interior plastering in summer?10
19.08.2018Strategically well-planned handover completion under building supervision11
17.12.2018What is set in stone in the building permit application?10
08.07.2019Bungalow 135 sqm: Floor plan + windows104
22.07.2019Window cracked - stress crack or external impact?11
12.07.2023Sealing of floor-to-ceiling windows from the outside74
16.01.2020Screed no functional heating after 7 weeks20
02.12.2020Additional costs / surcharge Higher windows48
22.12.2020Is it allowed to lay tiles on fresh screed?12
20.10.2021Wait with the windows until the roofer is finished?12
03.12.2021Heating phase, screed, window position20
25.02.2022Too much moisture in the single-family house after screed installation? Risk of mold?49
01.07.2022Construction delay without completion. The house simply is not finished21
03.03.2023Building permit application without height survey?15
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17