Our plan is as follows:
1. 5% 14 days after contract conclusion
2. 15% after completion of concreting work
3. 35% after assembly of the house
4. 5% after assembly of the stairs
5. 15% after installation of the windows
6. 10% after completion of the rough installation/sanitary facilities
7. 10% after completion of screed
8. 3% at move-in readiness
9. 2% after completion of remaining work