Thank you for the responses so far.
Update: we followed up again with two who were generally sympathetic to us.
There are now two contradictory statements regarding the construction period, which I cannot assess; what do you think:
One offers: construction time guarantee of 8 months from the start of construction, thereafter a penalty of 50 euros per day. He is confident and says this would be absolutely unproblematic.
The other says: he basically cannot guarantee anything, but as a guideline we should assume 13-15 months. Contractually, if necessary, he guarantees 15 months from the start of construction. You cannot classically build solidly with Poroton and concrete ceilings any faster without later having moisture problems due to shorter drying times.
What do the experts say? Is the second statement true or is it an excuse so that he remains flexible for other intermediate work on other construction sites simultaneously, etc.?