2020-11-17 09:56:54
- #1
Hello Hello,
after much back and forth, we have received an appointment to erect our house on November 25, 2020. At the beginning of September, we took the base slab out of the scope of services of our prefabricated house manufacturer and did it ourselves so that the house could still be erected this year.
Then today we got a call from our house manufacturer that the window company delivered the windows incorrectly (exterior color inside and interior color outside) and the erection appointment has been postponed indefinitely.
I understand that there is nothing we can do to have the house delivered this year, but is there a claim for compensation? Should we get in touch with a lawyer?
Thank you already for your thoughts and opinions.
Best regards
Susanne
after much back and forth, we have received an appointment to erect our house on November 25, 2020. At the beginning of September, we took the base slab out of the scope of services of our prefabricated house manufacturer and did it ourselves so that the house could still be erected this year.
Then today we got a call from our house manufacturer that the window company delivered the windows incorrectly (exterior color inside and interior color outside) and the erection appointment has been postponed indefinitely.
I understand that there is nothing we can do to have the house delivered this year, but is there a claim for compensation? Should we get in touch with a lawyer?
Thank you already for your thoughts and opinions.
Best regards
Susanne