Shell construction, removal of trades... the list can be almost endlessly continued. No house builder will have the acceptance date written into the contract, as the customer can almost cancel it at will.Why is the installation date important? The reference acceptance date is more decisive
In that case, I would also say: bad luck. Your builder will also try to wiggle out of the base slab issue because it involves external trades. If you want to increase the pressure, you can inform the builder that you reserve the right to charge any additional costs incurred. However, you would then have to prove these costs conclusively. This approach could, however, have a negative impact on your business relationship.I think the contract doesn’t say anything about the installation date, the only thing in the contract is that after completion of the base slab the house will be delivered no later than 8 weeks.