Doppelhaus_Ber
2023-09-19 12:46:22
- #1
Good day everyone,
our house construction company informed us yesterday that they do not want to continue building. Only against a one-time payment of an additional 18% of the total construction sum, including the 70% already paid in installments, they would continue without offering any guarantees. The contractually agreed construction period expired in mid-June. Alternatively, they would offer us a contract termination.
We will clarify how strong our legal position is and what the right reaction is with our lawyer tomorrow.
But now we face the problem that, most likely, no matter how things proceed, we will not continue building with our contractor and have to prepare to carry on ourselves.
This naturally leads to a lot of questions and a huge, seemingly insurmountable wall in our minds. The perhaps most important question for us: will we manage it, and if so, how do we cover the remaining budget, when the construction company told us that nothing can be done with the remaining approx. €74,000 and that an additional €45,000 would be needed to finish building.
Of course, we are willing to contribute as much as possible through our own work.
Currently, we have a shell with windows, front door, and a roof covering. On the ground floor, the bitumen welding membrane has been applied to the floor slab.
What we currently have in mind and what still needs to be done are:
- the insulation on the floor slab and in the roof,
- the rough electrical installation,
- the purchase and installation of the LWW pump, as well as laying the underfloor heating,
- the rough sanitary installation,
- the interior and exterior plaster,
- the screed,
- the final installation of electrical and sanitary systems,
- the interior doors,
- the floor and wall work,
- and the installation of the stairs.
Have we overlooked anything important? How would you continue planning in our situation?
our house construction company informed us yesterday that they do not want to continue building. Only against a one-time payment of an additional 18% of the total construction sum, including the 70% already paid in installments, they would continue without offering any guarantees. The contractually agreed construction period expired in mid-June. Alternatively, they would offer us a contract termination.
We will clarify how strong our legal position is and what the right reaction is with our lawyer tomorrow.
But now we face the problem that, most likely, no matter how things proceed, we will not continue building with our contractor and have to prepare to carry on ourselves.
This naturally leads to a lot of questions and a huge, seemingly insurmountable wall in our minds. The perhaps most important question for us: will we manage it, and if so, how do we cover the remaining budget, when the construction company told us that nothing can be done with the remaining approx. €74,000 and that an additional €45,000 would be needed to finish building.
Of course, we are willing to contribute as much as possible through our own work.
Currently, we have a shell with windows, front door, and a roof covering. On the ground floor, the bitumen welding membrane has been applied to the floor slab.
What we currently have in mind and what still needs to be done are:
- the insulation on the floor slab and in the roof,
- the rough electrical installation,
- the purchase and installation of the LWW pump, as well as laying the underfloor heating,
- the rough sanitary installation,
- the interior and exterior plaster,
- the screed,
- the final installation of electrical and sanitary systems,
- the interior doors,
- the floor and wall work,
- and the installation of the stairs.
Have we overlooked anything important? How would you continue planning in our situation?