Sounds not bad at first.
We have two more appointments next week, so we will continue to proceed step by step.

In order to better estimate the ancillary construction costs, we will probably start a soil survey now.
Although the plot is still being developed, the construction project manager of the new build area has also positively confirmed our request.
I assume that a simple survey should be sufficient here; the actual survey certainly does not make sense at this time and/or is not yet possible.
It would of course be unfortunate if a second soil survey became necessary - e.g. at the start of construction.

What are the experiences with TÜV Süd for construction-related quality control? Are there better or other good providers to recommend?
The scope sounds "healthy" to us at first, and of course there would also be the review of the construction contract.



I had looked at the portfolio and did not come to these prices - basements are also listed there.

Which house model did you buy?
Maybe share more details - many thanks

Best regards
 

NattySchw86

2019-03-18 23:37:32
  • #2
On the homepage, Schäfer Massiv does not list prices. We received a folder with all houses plus prices upon request. That was last summer. We were also informed that prices would be adjusted there. So we were lucky. But it fits without a basement. The basements are sometimes estimated with 40-50,000... Construction is expected to start in August, and you? (I cannot write privately because I am new here – we are building in OW)
 

CoolCat

2019-03-20 08:39:12
  • #3
So we now have an offer for the soil survey - designed for basement construction. The total is €1400 including the report and "technical consultation": €440 soil investigation €320 analysis €400 report & consultation plus VAT. We would probably remove the basement construction again, so the price would be slightly reduced. Overall, this seems to be a typical price (here measurements also have to be taken), or can certain items be omitted (e.g., the technical consultation in the report). Best regards
 

Nordlys

2019-03-20 09:39:37
  • #4
The expert report is a technical consultation. It consists of an analysis, that is, the land is composed in such and such a way, and a conclusion, therefore this and that should be founded there. It cannot be omitted, K.
 

CoolCat

2019-03-20 15:06:50
  • #5
Alright - I assume that is absolutely fine in terms of price as well. Acquaintances apparently only had [900€] here, but that was a few years ago.
 

CoolCat

2019-03-22 08:12:53
  • #6
What I would like to address now is the soil survey. I have repeatedly heard the opinion that it is not necessary if there is no basement. You would find out at the latest during the foundation construction and/or the foundation is not susceptible depending on the construction method. In short, my gut feeling says definitely do it. Is that correct? It also seems to me that the soil survey includes a check for contaminants - Laga-Tab (1.2.3 and 1.2.2), or is that too limited in scope?
 

Similar topics
15.01.2013Soil survey report for house construction10
09.09.2013Costs for soil replacement, soil survey for construction ground, clayey25
16.04.2014Cost of soil survey - Does the architect pay or do we?12
24.07.2014Soil assessment report, filling - additional costs?11
23.11.2014Soil report shocked us!!34
09.04.2015Ground too soft - drilling / soil survey not possible12
17.03.2015Soil survey in the Hannover area. Costs? Providers?10
03.09.2015Soil survey before purchasing property - who does it?14
26.11.2015Soil assessment - Threshold values for arsenic and heavy metals19
13.02.2017Soil survey before purchasing property?20
10.08.2016Soil report - silty and artificial fill11
17.10.2019Costs of soil assessment / geotechnical investigations34
27.03.2017Approximate costs for earth excavation based on soil investigation14
26.03.2018Is a soil report not possible before surveying the new construction area?16
08.05.2018Is a soil survey necessary? Better for cost estimation?17
12.12.2018Soil report prepared without my knowledge16
13.06.2019We need an additional soil report11
19.11.2019Preliminary contract for land due to soil survey17
25.02.2020What should we pay attention to in the soil report?21
10.07.2020Assessment of Soil Report - Experiences14

Oben