Wurzelxquadrat
2021-12-08 21:41:17
- #1
Hi everyone,
I want to ask for your advice because my general contractor is driving me crazy and costing me every last cent :)
After the price lock period passed, the general contractor already submitted a supplementary offer with enormous, partly certainly understandable, price increases. OK, with a gun to our heads, we agreed to the 15% additional costs. Then, shortly before the start of the civil engineering work, we were informed that additional civil engineering work would be necessary according to the created soil survey report. OK, the wound on our chests was still fresh, so we agreed to the additional 14,000 €. And here we now have the problem: The offer is basically structured as follows:
Item 1) 100 m³ installation of foundation cushion with MG FS 0/45 as the basis for the construction of .....terrace Price per m³ 59.60 € = 5960 €
Item 2) 50 m³ installation of foundation cushion with MG FS 0/45 as the basis for the construction of .... driveway Price per m³ 59.60 € = 2980 €
etc.
each with the addition: Billing according to weighbridges 2t/m³
In the invoice, however, he charges
Item 1) 115 m³ x 59.60 €
Item 2) 60 m³ x 59.60 €
and refers to the fact that he now brought in more, which is also apparent in the weighbridge tickets.
So he ultimately dug deeper and wider and therefore used more and is billing me for it.
Since this kind of money printing rubs me the wrong way, I naturally disputed the invoice.
In my opinion, it is the general contractor’s obligation to make a proper measurement and then make an offer accordingly.
Or he makes me an offer for the installation of the frost protection based on "per ton."
Sure, the addition is included, but for my feeling there are too many variables in this offer.
Basically, he can now calculate everything in any way he likes, no matter how much he installs.
What is your opinion on this case?
Am I mistaken here? Do I have to accept this?
Thanks in advance for your feedback
Regards
x
I want to ask for your advice because my general contractor is driving me crazy and costing me every last cent :)
After the price lock period passed, the general contractor already submitted a supplementary offer with enormous, partly certainly understandable, price increases. OK, with a gun to our heads, we agreed to the 15% additional costs. Then, shortly before the start of the civil engineering work, we were informed that additional civil engineering work would be necessary according to the created soil survey report. OK, the wound on our chests was still fresh, so we agreed to the additional 14,000 €. And here we now have the problem: The offer is basically structured as follows:
Item 1) 100 m³ installation of foundation cushion with MG FS 0/45 as the basis for the construction of .....terrace Price per m³ 59.60 € = 5960 €
Item 2) 50 m³ installation of foundation cushion with MG FS 0/45 as the basis for the construction of .... driveway Price per m³ 59.60 € = 2980 €
etc.
each with the addition: Billing according to weighbridges 2t/m³
In the invoice, however, he charges
Item 1) 115 m³ x 59.60 €
Item 2) 60 m³ x 59.60 €
and refers to the fact that he now brought in more, which is also apparent in the weighbridge tickets.
So he ultimately dug deeper and wider and therefore used more and is billing me for it.
Since this kind of money printing rubs me the wrong way, I naturally disputed the invoice.
In my opinion, it is the general contractor’s obligation to make a proper measurement and then make an offer accordingly.
Or he makes me an offer for the installation of the frost protection based on "per ton."
Sure, the addition is included, but for my feeling there are too many variables in this offer.
Basically, he can now calculate everything in any way he likes, no matter how much he installs.
What is your opinion on this case?
Am I mistaken here? Do I have to accept this?
Thanks in advance for your feedback
Regards
x